Locked In: Multi-Objective RL for the AI Data Center Build-Out

Satyapragnya Kar, Rajarshi Das, PR Panigrahi

Abstract

AI data center build-out is a multi-trillion-dollar, multi-decade infrastructure program. Yet siting, power procurement, and cooling decisions are still made with static, single-point scoring tools. These tools are evaluated once, on day-zero numbers. This is a poor fit. A site’s water, power, and carbon profile drifts substantially over the 10 to 20 year asset life. The governing decisions are also irreversible, and they bind capital and physical plant for years. We formalize long-horizon build-out as a tiered multi-objective Markov decision process. Strategic commitments are gated to discrete windows, incur switching costs, and energize only after source-dependent lead times. Operational dispatch is restricted to capacity that physically exists. We solve the problem with a preference-conditioned multi-objective agent that has a semi-Markov manager and worker hierarchy. The agent recovers a family of policies that a planner can steer across cost, carbon, water, and reliability at inference time. We validate long-horizon dynamics with a lightweight counterfactual rollout model. Across three commitment regimes (IRREVERSIBLE, REVERSIBLE, and COMMIT-ONCE) on real site data, preference conditioning yields a confirmed, steerable trade-off on both objective pairs in every regime. Imposing lock-in produces a more evenly covered frontier and a far more consistent rate of anticipatory retrofit ahead of a binding water-stress constraint than a freely reversible formulation. Finally, a compact counterfactual dynamics model tracks slow-moving state well. It is measurably outperformed by simple persistence on the water-stress axis. We report this limitation rather than obscure it. We release the environment, agents, baselines, and evaluation harness. All of them are grounded in real interconnection-queue, water-stress, and grid-emissions data.

1 Introduction

Site selection and build-out planning for AI data centers is conventionally treated as a one-shot scoring exercise. A candidate location is evaluated against present-day electricity price, grid carbon intensity, and water availability. It is then scored and filed. That approach is reasonable for a slowly varying resource base. It is not reasonable here. Global data center capital expenditure is projected to reach nearly 7trillionby2030[19].Annualdatacenterelectricitydemandisontracktoreachroughly945TWhby2030[13;11].Roughly2,060GWofgenerationandstoragecapacitysitsinU.S.interconnectionqueues,withtypicalmulti−yearwaitstocommercialoperation[24].Waterconsumptionisprojectedtogrowbyasmuchas1707 trillion by 2030 [19]. Annual data center electricity demand is on track to reach roughly 945 TWh by 2030 [13; 11]. Roughly 2,060 GW of generation and storage capacity sits in U.S. interconnection queues, with typical multi-year waits to commercial operation [24]. Water consumption is projected to grow by as much as 170% over the same period [33]. Hyperscaler capital commitments already run into the hundreds of billions of dollars through 2027 [4]. All-in build costs run from roughly11 million per MW up to the tens of millions once compute fit-out is included [15]. Together, these figures imply three things. The resource base drifts within a single asset life. When capacity energizes is as consequential as what is procured. A single build phase is a multi-billion-dollar, effectively irreversible commitment. None of this can be expressed by a score computed once.

Tackling Climate Change with Machine Learning: workshop at NeurIPS 2026.

Planning where, how, and when to build AI data center capacity (siting, power procurement, and cooling) is a sequential decision problem, not a scoring problem. There are two reasons. First, the objectives are contrastive. There is no single optimum, only a Pareto frontier across cost, carbon, water, and reliability. Second, decisions are irreversible on operationally meaningful timescales, so early commitments constrain the entire remaining sequence. A formulation that permits free, instantaneous switching collapses to myopic per-period scoring. This is exactly the practice this work aims to displace.

We make three contributions. First, we introduce a tiered multi-objective MDP for build-out planning. It has gated retrofit windows, switching costs, and source-dependent energization lead times calibrated to real interconnection-queue data (Section 2). Second, we present a preference-conditioned agent with a semi-Markov manager and worker hierarchy. The hierarchy separates decade-scale commitment from quarterly dispatch while preserving inference-time steerability. We also provide a lightweight counterfactual dynamics model for validating long-horizon behavior (Section 3). Third, we report an empirical study across three commitment regimes on real, grounded site data. The study isolates the contribution of irreversibility to frontier quality, steerability, and anticipatory behavior (Section 5). Related work on RL for computing and energy systems, multi-objective RL, hierarchical RL, and robust or non-stationary RL is summarized in Appendix A.

This paper is one of a small family of companion studies on the AI build-out. In Methane First [6], we study a narrower, single-decision slice of the same planning problem. The question is how a fixed annual budget should be split between methane leak repair and carbon capture across a fleet of on-site gas-powered data centers. That problem is small enough to solve exactly by dynamic programming. A model-free RL policy recovers the exact optimum in nearly all runs. This supports using RL on the richer, multi-objective, multi-commitment setting studied here, where no exact solution is available (Appendix A). A second companion, Watts If? [5], benchmarks language models on counterfactual reasoning about what each commitment in a build-out rules out (see Section 6).