Watts If? A Benchmark for Counterfactual Reasoning About the AI Data Center Buildout

Pankaj Chouhan, Rajarshi Das, Aditya Dubey, Manminder Tomar, Sreekar Reddy, Samta Sharma, Satyapragnya Kar, PR Panigrahi

Pankaj Chouhan ∗^{*}

AlphaInfra

pankaj.c@alphainfra.ai

Rajarshi Das ∗^{*}

AlphaInfra

rajarshi.das@alphainfra.ai

Manminder Tomar

AlphaInfra

manminder.t@alphainfra.ai

Aditya Dubey

AlphaInfra

aditya.d@alphainfra.ai

Sreekar Reddy

AlphaInfra

sreekar.r@alphainfra.ai

Satyapragnya Kar ∗^{*}

New York University

sk13001@nyu.edu

Samta Sharma

AlphaInfra

samta.s@alphainfra.ai

PR Panigrahi

Envana Software Solutions

pr.panigrahi@envana.com

Abstract

An AI data center is committed years before it draws a watt: a few discrete choices — grid or on-site gas, evaporative or dry cooling, which county to file in — fix its capital, water draw, and carbon path, and LLMs are now asked to help screen them with no test of whether they track what each commitment rules out. We introduce DCBench-440, with two arms reported separately: 200 generative questions over STRIPS worlds for five US deal archetypes, with search-verified gold answers and no tested shortcut above 12.0% on any question type, and 240 multiple-choice questions grounded in quoted site records, emission equations, and stated scenarios. Across open-weight deployments, accuracy spans 12.5–71.5% (generative) and 58.3–92.5% (multiple choice). One skill fails everywhere: asked to list every action available at a decision gate, no model exceeds 4.0% exact match. The strongest list 72–85% of the actions that would change the project’s state but omit most permitted actions that change nothing; with those excused, the best exact match is still 24.0%. Code, data, and other materials are available upon request.

1 Introduction

The AI data center buildout is one of the largest capital programs in history, roughly 7trillionby2030,withpowerandwaterdemandclimbingalongside[6,8,11,13,20,29].Thehardquestionistheorderofcommitments.TakeadeveloperweworkwithintheUS:7 trillion by 2030, with power and water demand climbing alongside [6, 8, 11, 13, 20, 29]. The hard question is the order of commitments. Take a developer we work with in the US:^{1}$one site plans 550 MW of on-site gas and holds every permit but the air permit; a second needs 750 MW from the grid and is one of seven waiting on the utility; a third is bare land with a gas pipeline across it. On-site gas skips a grid queue where capacity now waits three to seven years [22], but takes on turbines, fuel supply, and emissions permits. Developers are taking that trade: 61% of those surveyed name on-site power their primary strategy when the grid is the bottleneck [4], and 124 GW of on-site gas has been announced for US data centers [5]. The choices that fix a site’s water and carbon path — evaporative or dry cooling, on-site gas or grid — also fix its capital cost and date of first power, so at each gate the question is what a commitment rules out.

∗^{*}Equal contribution.

1^{1}Site names and counties are withheld. Figures are from the developer’s own financing materials.

Preprint.

Language models are entering this work as screening and diligence aids, and LLM analysis of corporate, policy, and media sources already feeds projections of data-center power demand [7]. A fluent answer is not a plan. A wrong number can be checked; an option the model never mentions — a permit that must come first, a route that a choice forecloses — cannot.

DCBench-440 measures that second kind of failure. It contributes:

• a generative arm applying ACPBench Hard’s eight question types [16] to five US deal archetypes, selected against shortcuts (Section 3.1);

• an independent multiple-choice arm (Section 3.2);

• an evaluation of 11 deployments of 7 open-weight models with intervals, paired tests, settings, and cost (Section 4, Appendix B); and

  • a diagnosis of the failure every model shares: exact enumeration of the actions available at a gate, that is, listing every step the project could take next.