arXiv:2609.05578Planning and Scheduling Business Processes under Control-Flow Uncertainty
Michel Kunkler[0000-0002-1920-7322], Stefanie Rinderle-Ma[0000-0001-5656-6108]
Technical University of Munich, Germany TUM School of Computation, Information, and Technology {michel.kunkler,stefanie.rinderle-ma}@tum.de
Abstract. Scheduling activities in business processes can improve efficiency (e.g., reduce makespan), but is challenging because the exact sequence of activities required to complete a case is often uncertain due to decisions based on data that emerges during execution. Nevertheless, probabilistic information regarding such decisions can often be estimated or derived from historical execution logs, and can help anticipate which execution paths are likely to lead to successful completion. Planning with particular execution paths affects feasibility, i.e., the probability of successful completion, and the expected number of superfluous activities that are planned but never executed. We frame the problem as a chance-constrained optimization problem and present two formulations: A decomposed approach with two stages, a planning stage that minimizes the expected number of superfluous activities subject to a feasibility constraint, and a scheduling stage that minimizes the makespan over the planned activities; and an integrated approach that combines planning and scheduling into a single formulation. Evaluation on two real-world and one synthetic dataset shows that the integrated approach yields superior makespans but is intractable at scale, while the decomposed approach scales to large settings.
Keywords: Business Processes · Chance Constraints · Scheduling
1 Introduction
Scheduling the execution of activities in business processes can improve operational efficiency, e.g., by reducing the makespan of cases and improving resource utilization. Moreover, schedules provide visibility into the future, which can help resources prepare for their upcoming activities and identify capacity bottlenecks, thereby supporting management decisions regarding business process improvements [3]. Formalizing and solving an optimization problem for scheduling the execution of business process activities is challenging for several reasons: high computational complexity, modeling complexity from control-flow or resource constraints, and the degree of uncertainty in business process execution [10]. Current work on scheduling activities of business processes has primarily addressed setting up computationally tractable optimization models and capturing
M. Kunkler, S. Rinderle-Ma
a rich set of control-flow and resource constraints [1,13], or addressed uncertain activity durations [7] and resource availability [9,12].
A key driver of uncertainty in business process execution is that the sequence of activities required to successfully complete a case is often not known with certainty beforehand, e.g., due to runtime constraints or decisions based on data revealed during execution. Consequently, the exact set of activities that must be scheduled for a case is not known in advance. While this issue has been acknowledged [10,7] and termed control-flow induced uncertainty [10], existing work has either focused on scheduling only until the course of the business process can be determined with high certainty [7] or adopted online resource allocation approaches [9,12]. Both strategies undermine some of the benefits of scheduling, e.g., by preventing resources from preparing for their upcoming activities.
In this work, we address the problem of planning and scheduling the activities of cases under control-flow induced uncertainty until case completion. We assume that a schedule for a case is feasible if the scheduled activities are sufficient to complete it. Moreover, we assume that any unnecessarily scheduled activity can be skipped. We refer to such activities as superfluous. The key idea of this work is to formulate activity selection as a chance-constrained optimization problem, in which activities are selected such that a predefined case feasibility threshold is satisfied while minimizing an optimization objective. We present two approaches. In the i) decomposed approach, we first determine the set of activities to be scheduled by solving a planning problem that minimizes the expected number of superfluous activities subject to a feasibility constraint; in the second step, the planned activities are scheduled to minimize the makespan, i.e., the completion time of the final activity. In the ii) integrated approach, planning and scheduling are combined into a single formulation that directly minimizes the makespan subject to a feasibility constraint. The decomposed approach allows exclusive activities to overlap, since at most one will actually execute. The integrated approach also allows non-exclusive activities to overlap, which can be beneficial when their joint execution probability is low, keeping the impact on feasibility minor.
An exemplary business process with control-flow uncertainty is shown in Fig. 1. It depicts a repair center with an exclusive choice (with two branches and their branching probabilities and ) and a loop (with redo probability ). Below the process model, an example schedule is shown for two cases and three resources (one per swim lane). In this schedule, the Repair and Quality Control (QC) activities are planned twice for each case. Since the probability that both cases require a second loop iteration is low, these activities are scheduled to overlap, which can be achieved by the proposed integrated approach.
We formalize both approaches, provide constraint programming implementations and evaluate them on two real-world and one synthetic dataset. The results show that the integrated approach yields superior makespans but is intractable at scale, while the decomposed approach scales to large settings.

Fig. 1. Exemplary schedule for two cases with overbooking of unlikely activities with a feasibility of and an expected number of feasible cases .
The remainder of this paper is structured as follows. Sects. 2 and 3 present the decomposed and integrated approaches, respectively. Sect. 4 evaluates both approaches, Sect. 5 discusses related work, and Sect. 6 concludes.
Definition 1 (Stochastic Process Tree). Let be a stochastic process tree which consists of sets of operators (sequential , parallel , exclusive choices , redo loops ), observable activities , silent transitions and a designated root . Let denote the tree's nodes, i.e., . The root has exactly one child, nodes have exactly two ordered children (do-part , redo-part ), the other operator nodes (, , ) have at least two children and the activity nodes ( and ) are leaf nodes. Let denote the transition probability of branch from an exclusive choice , with , and the redo probability of a redo loop . We assume stationarity, i.e., and remain constant over loop iterations.
M. Kunkler, S. Rinderle-Ma
We define the following selector functions on a node of . Since is an ordered tree, children of every node are indexed from left to right, starting with 1: Let denote the set of children of ; let denote the -th child of , let denote the parent node of ; let denote the branch index of within its parent; let denote the set of strict ancestors of , let denote the descendants of (including itself); and let denote the left siblings of . For two activity nodes and , we write if is to the left of in the process tree, i.e., .
The stochastic process tree for the business process in Fig. 1 is shown in Fig. 2.

Fig. 2. Stochastic process tree for the repair process.
Given a stochastic process tree, we first solve a chance-constrained planning problem that selects exclusive-choice branches and loop iteration counts subject to a predefined case feasibility threshold. Because superfluous activities occupy resources at runtime without contributing to the process outcome, we minimize their expected number to reduce unnecessary resource contention in the subsequent scheduling stage. The planned activities are then scheduled to directly minimize the makespan, exploiting mutual exclusivity to allow overlapping resource assignments. We develop both stages first for a single case and then extend them to the multi-case setting.
2.1 The Planning Problem
Given a stochastic process tree, we define the decision variables for branch selection and loop unrolling, derive the resulting case feasibility and expected number of superfluous activities, and formulate the planning problem as a chance-constrained optimization problem.
Definition 2 (Decision Variables Planning Problem). For each exclusive choice node , let denote whether branch is to be planned. For each loop node , let denote the number of planned loop iterations, yielding executions of the do-part and executions of the redo-part.
Definition 3 (Case Feasibility). Let be a stochastic process tree, the decision variables, and a node in . Then the node feasibility of is defined as:
Based on the node feasibility , we define the case feasibility as:
We compute top-down from the root via the node feasibility , the probability that execution of is feasible given . For an exclusive choice , only selected branches contribute, since taking an unselected branch at runtime renders the execution infeasible. For a loop , the do-part executes at least once and each further iteration contributes with probability , depending on both the do- and redo-parts, yielding , whose closed form appears in Eq. 1.
Definition 4 (Superfluous Activities). Let be a stochastic process tree and the decision variables. The planning count gives the number of times activity is planned under selection (where denotes the parent of , cf. Def. 1). The expected execution count gives the expected number of runtime executions of . The expected number of superfluous activities sums the difference over activities .
M. Kunkler, S. Rinderle-Ma
We compute and bottom-up; both depend on the activity's exclusive choice and loop ancestors. For , the activity counts as planned only if every ancestor is selected. Its base value 1 is multiplied by for each loop ancestor in whose do-part it lies, and by for each in whose redo-part it lies. For , the base value 1 is multiplied by at each ancestor and by the expected iteration count (do-part) or (redo-part) for each loop ancestor; both sums admit closed forms used in Eq. 4.
Fig. 3 illustrates the node feasibility for the running example as well as the planned and expected execution counts.

Fig. 3. Stochastic process tree with selection , node feasibility in red, planned and expected executed counts in blue.
Solving the Planning Problem Based on the above, we can write the planning problem as a mixed-integer nonlinear program (MINLP) (Eq. 6) that minimizes the expected number of superfluous activities while satisfying a case feasibility threshold .
2.2 The Scheduling Problem
Given a selection from the planning problem, we construct a scheduling problem that minimizes the makespan of the planned activities, i.e., the time until the end of the last activity in a case, e.g., makespan = 7 for the blue case in Fig. 1. To this end, we unroll the process tree and remove non-selected branches to obtain the set of activities and their precedence constraints and their mutual exclusivity. We then identify activities that are mutually exclusive; since at most one of them will be executed at runtime, they can be assigned to the same resource concurrently. Finally, we formulate the scheduling problem as a MINLP.
Unrolled and Branch Selected Process Tree Given a selection , we transform the process tree by removing non-selected branches and unrolling loops. For every , the node and its descendants are removed. Each loop node is unrolled according to : if , it is replaced by its do-part . For , it is replaced by a sequential composition beginning with the do-part, where each subsequent iteration is an exclusive choice between a silent transition (loop exit) and the redo-part followed by the do-part and the same choice recursively, terminating after iterations. Any schedule must respect the precedence orders set out by the original process tree; this equally applies to the unrolled and branch-selected process tree. Otherwise, important functional or compliance ordering constraints would be violated, e.g., examining the patient before surgery. Hence, an activity can only start after all its predecessors have completed where , i.e., all descendants of all left siblings , where is itself or any ancestor of with .
Since at most one branch of an exclusive choice is executed at runtime, mutually exclusive activities can share a resource in overlapping time slots.
Definition 5 (Mutual Exclusivity). Two activities are mutually exclusive () if there exists a common exclusive-choice ancestor with distinct children such that and . The set of activities exclusive to is .
Scheduling Formulation We formalize the scheduling problem as a joint resource-assignment and activity-start-time decision problem to minimize the makespan. For each activity , let be an interval variable with accessors start( ), end( ), dur( ), and overlapping( ) which equals 1 iff and share a common time point. Let be the set of resources, and for each , let be the processing time of on and the allocation variable. The formulation in Eq. 7 minimizes the makespan (7a), sets the processing time per resource assignment (7b), enforces precedence (7c), ensures each activity is assigned to exactly one resource (7d), and prevents temporal overlap of non-mutually-exclusive activities on the same resource (7e).
M. Kunkler, S. Rinderle-Ma
2.3 Multi-Case Planning and Scheduling
In practice, multiple cases must be scheduled concurrently, so we extend the decomposed approach to cases. The per-case feasibility does not directly convey how many cases are expected to complete successfully; we therefore adopt the expected number of feasible cases as the chance constraint. We reuse the MINLP (Eq. 6) with per-case threshold , where denotes the required expected number of feasible cases, and apply the resulting selection uniformly to all cases. Since precedence and mutual exclusivity apply within each case, the scheduling formulation extends to cases by taking the union of the unrolled process trees. A schedule from the decomposed approach for the two cases from the running example is shown in Fig. 4. A lower number

Fig. 4. Schedule generated by the decomposed approach for the running example with two cases.
of superfluous activities could in principle be achieved by per-case planning, i.e., composing copies of the process tree in parallel, but this renders the planning problem intractable for large ; the integrated approach in Sect. 3 addresses this by jointly optimizing planning and scheduling.
3 Integrated Approach
The decomposed approach has two limitations that can affect the optimality of the resulting schedule, which we address in the integrated approach: First, minimizing superfluous activities in the planning stage does not necessarily lead to a minimal makespan in the scheduling stage, as selecting a branch with more (superfluous) activities can be beneficial for the makespan, e.g., when this avoids scheduling on a bottleneck resource. Second, the decomposed approach only allows exclusive activities to be scheduled concurrently on the same resource. Additionally allowing non-exclusive activities to overlap on a resource can further shorten the makespan. This holds especially in the multi-case setting where it can be meaningful to, e.g., schedule two activities from two different cases that both have low execution probability concurrently as this will only lead to a minor decrease of (see Fig. 1). We therefore present an integrated approach that combines planning and scheduling into a single formulation, allowing per-case selections and the overlapping scheduling of non-exclusive activities.
Definition 6 (Decision Variables Integrated Problem). For each case and each exclusive choice node , let indicate whether branch
is selected for . For each loop node , let denote the number of planned iterations, yielding executions of the do-part and executions of the redo-part.
We obtain unrolled-and-selected process trees, from which we directly derive precedence and mutual exclusivity relationships and compute the set of activities for a scenario and its probability.
Definition 7 (Unrolled-and-Selected Process Tree). For case and selection , the unrolled-and-selected process tree is obtained from by: (i) deleting, for every and every branch with the subtree rooted at ; if only one branch of remains, is replaced by that branch; (ii) replacing the do-subtree of each loop by a sequential composition of unrolled do-copies interleaved with unrolled redo-copies (do, redo, do, ..., redo, do), and its redo-subtree by a placeholder that is never visited at runtime. We write for nodes of and for the original-tree node that instantiated (undefined on the placeholder ).
Unlike the unrolling in Sect. 2, we flatten the loop and retain rather than introducing exit-s, so that every and in carries the original or .
Definition 8 (Planned Activities). The set of planned activities under selection is
with . For convenience, we write for with . We lift the precedence constraint in Eq. 7c to planned activities by , with applied to .
Expected Case Feasibility with Overlapping Activities Since the integrated formulation permits non-exclusive activities to overlap on the same resource, case feasibility no longer depends solely on branch selection and loop unrolling: for non-exclusive overlapping activities, multiple activities may need to execute, reducing . We formalize this by defining (i) an activity priority order that determines which activity runs when overlapping allocations conflict, (ii) the execution probabilities of overlapping activities, and (iii) a lower bound on the expected number of feasible cases.
Definition 9 (Activity Priority Order). When two planned activities and are allocated to overlap on the same resource, only the higher-priority one can execute; we say has higher priority than iff , with:
(9)
M. Kunkler, S. Rinderle-Ma
Definition 10 (Overlapping Activities). Two activities are overlapping if they are allocated to the same resource and have overlapping time intervals. The set of activities overlapping with given intervals I and resource assignments z is denoted .
Since an activity can overlap with multiple activities from another case, and those activities may have correlated executions, we can no longer treat each overlap as an independent threat to case feasibility. To capture the joint execution probabilities of overlapping activities, we introduce a per-case scenario-based approach which exploits three structural facts: (i) scenarios across cases are independent; (ii) exclusive planned activities can never be executed together; (iii) within each scenario, activity executions are deterministic, resolving any remaining intra-case dependencies.
Definition 11 (Execution Scenario). An execution scenario for case is a runtime realization drawing, independently at each reached visit, a branch at every with and an iteration count at every with ; let and denote the sets of and nodes visited in . is planning-feasible, , iff all draws fit the plan: and ; is finite despite the infinite scenario space. For , its probability and visited activities are:
(11)
Definition 12 (Exclusive Planned Activities). We lift the mutual exclusivity relation of Eq. 5 (applied to ) to planned activities; two are exclusive only if they belong to the same case:
Definition 13 (Threats and Intra-Case Feasibility). For an activity set , let contain the threats to activities in , i.e., activities that overlap with some , have higher priority than a, and are non-exclusive to a. Further, let the intra-case feasibility indicator be 1 iff scenario of case contains no internal conflict, i.e., no activity of is threatened by another non-exclusive activity of . Formally:
(13)
Building on the above definitions, we can now compute the expected number of feasible cases.
Definition 14 (Expected Feasible Cases). For a case with threat activities , the case threat probability is the probability that another case executes at least one of its own activities in , i.e., realizes one of 's threats; it uses a tail-absorbing scenario weight that differs from only at the maximum loop iteration. The overlap-adjusted case feasibility is the probability that case completes without a realized threat; it sums over planning-feasible scenarios, with handling intra-case threats and a product over handling cross-case threats. The expected number of feasible cases sums over cases; it is a lower bound, since a cross-case higher-priority activity need not be executed when its case is already infeasible.
(14)
accounts for runtime realizations that exceed the plan: if a loop requires more than its planned iterations, case still executes all planned iterations before the infeasibility becomes apparent, and the activities executed in them may threaten other cases. therefore adds this tail probability ( for a loop with planned iterations) to the scenario with the maximum iteration count by omitting its final factor. With instead, would understate the threat probability and would not be a lower bound.
The Integrated Multi-Case Scheduling Problem Formulation The objective is again to minimize the makespan for a given expected number of feasible cases threshold . Unlike the decomposed formulation, the decision variables and constraints are not fixed a priori, as the set of planned activities , their precedence relations, and the interval and assignment variables all depend on the selection . The formulation is therefore stated in a declarative way over the variable-size sets induced by ; in practice, it can be instantiated by unrolling loops to a sufficient maximum bound with indicator variables disabling unused iterations, or solved directly via constraint-programming solvers that natively support optional and variable-length structures. Each loop ancestor multiplies the number of XOR and loop occurrences in , so grows exponentially in loop-nesting depth. For each planned activity, we introduce an interval , .
M. Kunkler, S. Rinderle-Ma
4 Evaluation
In this section, we evaluate the performance and the applicability of the proposed approaches. We first describe the business processes used for evaluation, followed by the implementation details and the evaluation metrics used to compare the approaches. Finally, we present and analyze the results of the evaluation.
4.1 Business Processes
We select three business processes with varying characteristics to evaluate the approaches under different conditions. The business processes are selected based on their complexity, resource requirements, and the availability of event logs that contain activity durations. The selected business processes are: Repair Shop, an artificial repair center whose process model and branching/looping probabilities are shown in Fig. 1; BPIC-14I, a real-world process from the Business Process Intelligence Challenge (BPIC) 2014, based on IT service management data from Rabobank Group ICT; and BPIC-17W, a real-world process from BPIC 2017, containing event data from a loan application process at a Dutch financial institute: we selected only the workflow (W) activities, representing the internal work steps performed by bank employees. The structural characteristics of the business processes are summarized in Tab. 1.
Table 1. Structural characteristics of the evaluation business processes.
| Act | ◇ | ◇ | ∘ | |→| | τ | Nodes | Depth | |
|---|---|---|---|---|---|---|---|---|
| Repair Shop | 6 | 1 | 1 | 1 | 2 | 1 | 12 | 5 |
| BPIC-14I | 6 | 1 | 0 | 0 | 0 | 0 | 7 | 2 |
| BPIC-17W | 8 | 9 | 3 | 8 | 4 | 17 | 49 | 13 |
We discovered the process trees for the two real-world business processes using the inductive miner [11], with branching and looping probabilities obtained by replaying the event log on the discovered process tree. Resource capabilities and processing times are derived from the event logs, where a resource is permitted for an activity if observed executing it at least once, and durations are estimated as medians. To account for varying daily availability, we select a representative day closest to the mean active resource count, yielding 8 of 14 resources for BPIC-14I, and 28 of 145 for BPIC-17W. For the Repair Shop business process, we generate 9 synthetic resources with varying capabilities.
4.2 Implementation
The prototypical implementation¹ is based on constraint programming models using Google OR-Tools CP-SAT². Since CP-SAT operates exclusively over integer variables, all floating-point probabilities are scaled to integers with a fixed-point scale factor.
Decomposed Approach Since CP-SAT does not natively support power operations, which are required for the activity planning part, the -dependent geometric-series coefficients are precomputed for a sufficient set of values () and implemented as lookup tables. The total time budget is shared: the planning phase receives at most half of the budget, and the remaining wall-clock time is passed to the scheduling phase.
Integrated Approach The integrated formulation is encoded as a single CP-SAT model. Since CP-SAT does not support a dynamic number of variables, loop unrolling is limited to a maximum iteration bound ().
Baseline Approach A direct comparison with existing approaches is precluded: they either schedule only up to the next uncertain decision point [7] or allocate resources online during execution [9,12], and thus yield no a-priori schedule until case completion whose makespan and feasibility could be compared against ours. We therefore compare our approaches with a baseline that selects the single most probable execution using the probabilities of exclusive choices and the expected loop length. Hence, it does not consider the expected feasible cases constraint . The planned activities from the baseline approach are scheduled using the same scheduling logic as for the decomposed approaches, so its scheduling solutions may not be optimal.
4.3 Evaluation Results
We ran the evaluation on a machine with an AMD Ryzen 9 PRO 8945HS CPU and 32 GB of RAM, with a 20-minute time limit per run. The results are summarized in Tab. 2. We report the expected number of feasible cases of a solution, indicating how closely the solution meets the feasibility constraint , the makespan of a solution, the number of scheduled activities, reflecting the total resource workload including potentially superfluous activities, and the solver duration and optimality flag for each phase. For those runs marked with “-”, no feasible solution was found within the time limit.
¹ https://github.com/ltsstar/BusinessProcessPlanningScheduling/ ² https://developers.google.com/optimization
M. Kunkler, S. Rinderle-Ma
Table 2. Evaluation results (N : number of cases, E : expected feasible cases constraint, : expected feasible cases, MS : makespan (s), SA : scheduled activities, PD : planning duration (s), PO : planning optimality, SD : scheduling duration (s), SO : scheduling optimality, ID : integration duration (s); baseline : single-path selection (argmax branch, expected loop length), independent of E; bold: best value per row among the decomposed and integrated approaches ( closest to E from above, i.e., meeting the feasibility constraint most tightly, lowest MS, fewest SA); underlined: a baseline MS or SA that matches or beats this best, which the single-path baseline may attain while violating the feasibility constraint, i.e., )
| Settings | Baseline | Decomposed | Integrated | |||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| P | N | E | MS | SA | SO | MS | SA | PD | PO | SD | SO | MS | SA | ID | Opt | |||
| Repair Shop | 1 | 0.6 | 0.56 | 384 | 5 | ✓ | 0.86 | 384 | 6 | 0.01 | ✓ | 0.01 | ✓ | 0.86 | 384 | 6 | 0.08 | ✓ |
| 1 | 0.8 | 0.86 | 384 | 6 | 0.01 | ✓ | 0.01 | ✓ | 0.86 | 384 | 6 | 0.08 | ✓ | |||||
| 5 | 3 | 2.80 | 960 | 25 | - | 4.30 | 960 | 30 | 0.01 | ✓ | 1199 | - | 3.01 | 624 | 30 | 433 | ✓ | |
| 5 | 4 | 4.30 | 960 | 30 | 0.01 | ✓ | 1199 | - | 4.00 | 912 | 36 | 1200 | - | |||||
| 50 | 30 | 28.00 | 9600 | 250 | - | 43.00 | 9600 | 300 | 0.01 | ✓ | 1199 | - | - | - | - | - | - | |
| 50 | 40 | 43.00 | 9600 | 300 | 0.01 | ✓ | 1199 | - | - | - | - | - | - | |||||
| BPIC-14I | 1 | 0.6 | 0.79 | 99 | 1 | ✓ | 0.79 | 99 | 1 | 0.02 | ✓ | 0.01 | ✓ | 0.79 | 99 | 1 | 0.05 | ✓ |
| 1 | 0.8 | 1.00 | 175 | 2 | 0.01 | ✓ | 0.01 | ✓ | 1.00 | 175 | 3 | 0.05 | ✓ | |||||
| 5 | 3 | 3.94 | 347 | 5 | ✓ | 3.94 | 347 | 5 | 0.01 | ✓ | 0.01 | ✓ | 3.04 | 297 | 18 | 0.26 | ✓ | |
| 5 | 4 | 5.00 | 357 | 10 | 0.01 | ✓ | 0.03 | ✓ | 4.12 | 310 | 19 | 0.24 | ✓ | |||||
| 50 | 30 | 39.35 | 1830 | 50 | - | 39.35 | 1830 | 50 | 0.06 | ✓ | 1199 | - | - | - | - | - | - | |
| 50 | 40 | 49.96 | 2170 | 100 | 0.01 | ✓ | 1199 | - | - | - | - | - | - | |||||
| BPIC-17W | 1 | 0.6 | 0.16 | 721 | 7 | ✓ | 0.61 | 1483 | 21 | 0.07 | ✓ | 0.25 | ✓ | 0.60 | 768 | 66 | 35 | ✓ |
| 1 | 0.8 | 0.80 | 1895 | 41 | 0.05 | ✓ | 1.79 | ✓ | - | - | - | - | - | |||||
| 5 | 3 | 0.80 | 863 | 35 | ✓ | 3.07 | 1746 | 105 | 0.06 | ✓ | 1199 | - | - | - | - | - | - | |
| 5 | 4 | 4.02 | 2258 | 205 | 0.06 | ✓ | 1200 | - | - | - | - | - | - | |||||
| 50 | 30 | 8.03 | 5602 | 350 | - | 30.67 | - | - | 0.07 | ✓ | - | - | - | - | - | - | - | |
| 50 | 40 | 40.16 | - | - | 0.05 | ✓ | - | - | - | - | - | - | - | |||||
For the decomposed approach, the planning phase is trivially fast and always optimal, while scheduling is the clear bottleneck. Still, a feasible schedule is found for every configuration except BPIC-17W with , the most complex process with the highest resource, case, and expected-feasible-case counts. The integrated approach scales poorly, mostly failing to find a feasible solution for larger configurations within the time limit. Where it does solve (Repair Shop and BPIC-14I with , BPIC-17W with ), it yields shorter makespans than the decomposed approach, typically at the cost of more scheduled activities. The baseline approach's feasibility varies by process: for BPIC-14I, with its single exclusive choice, it matches the decomposed approach at the 60% feasibility constraint; for the more complex BPIC-17W, feasibility is extremely low; for Repair Shop, feasibility is lower than the other approaches but with the same makespan as the decomposed approach.
5 Related Work
Planning and scheduling of activities has been addressed in the literature in different domains, including business process management (BPM), operations research (OR), and AI planning.
Scheduling and Resource Allocation in Business Process Management. In our prior survey [10], we identified that existing work on scheduling business process activities often treats the branch taken at exclusive choices as a decision variable and formulates optimization problems that select a single best path (e.g. [1]). By contrast, in this work, the branch selection is a stochastic outcome necessitating a formulation that plans for sufficiently many paths to guarantee a target level of feasibility. Some approaches explicitly address the control-flow induced uncertainty by either scheduling as long as certainty is relatively high [7] or presenting online resource-allocation approaches instead of scheduling the whole case [9,12].
Resource-Constrained Project Scheduling (RCPSP). A related prominent problem in OR is the RCPSP, which only involves scheduling a fixed set of activities with known durations and precedence constraints, but does not consider uncertainty in the activity network structure [6]. The RCPSP with alternative subgraphs (RCPSP-AS) [8] is similar to our problem formulation: the project network contains alternative execution paths, resembling exclusive choices; however, the choice of alternatives is a decision variable (as in [1]).
AI Planning. AI planning approaches have also addressed the problem of planning and scheduling under uncertainty. In particular, conformant probabilistic planning (CPP) seeks solutions that conform to uncertain outcomes, similar to our approach [5]. Chance-constrained CPP has also been studied: closest to our approach, [2] uses probabilistic simple temporal networks (a graph model without uncertain control flow, but with uncertain activity durations) and LP relaxation to compute a chance-constrained schedule.
6 Discussion and Conclusion
In this work, we addressed planning and scheduling of business process activities under control-flow induced uncertainty until case completion. We presented a decomposed approach with sequential planning and scheduling stages, and an integrated approach combining both in a single formulation; both use chance-constrained optimization to select activities such that a predefined case feasibility threshold is met while minimizing the makespan. The evaluation reveals a trade-off between solution quality and scalability: the integrated approach can yield superior makespans but scales poorly. The decomposed approach, in contrast, reliably finds feasible schedules across nearly all tested configurations. In practice, scheduling cases until completion rather than only up to the next decision point allows resources to prepare for upcoming activities and enables reliable commitments towards customers. The feasibility threshold acts as a management lever balancing the risk of rescheduling against reserved but potentially unused capacity, comparable to overbooking. Since all required inputs can be discovered from event logs, the approaches integrate into existing process-aware information systems with little modeling effort. A limitation of both formulations is that branch selection for exclusive choices within loops is uniform across
M. Kunkler, S. Rinderle-Ma
iterations, which can lead to suboptimal plans, since later iterations with lower execution probability could benefit from planning fewer branches. Future work could address iteration-dependent branch selection and incorporate processing time uncertainty alongside control-flow uncertainty.
References
-
van der Aalst, W.M.P.: Petri net based scheduling. OR Spektrum 18(4), 219–229 (1996)
-
de Rodrigues Quemel e Assis Santana, P.H., Vaquero, T., Toledo, C., Wang, A.J., Fang, C., Williams, B.C.: PARIS: A polynomial-time, risk-sensitive scheduling algorithm for probabilistic simple temporal networks with uncertainty. In: ICAPS 2016. pp. 267–275 (2016)
-
Aytug, H., Lawley, M.A., McKay, K., Mohan, S., Uzsoy, R.: Executing production schedules in the face of uncertainties: A review and some future directions. Eur. J. Oper. Res. 161(1), 86–110 (2005)
-
Cry, P., Horváth, A., Ballarini, P.: Stochastic process trees: A formal framework for stochastic process discovery. In: ICPM. IEEE (2025)
-
Geffner, H., Bonet, B.: A Concise Introduction to Models and Methods for Automated Planning. Springer Cham (2013)
-
Hartmann, S., Briskorn, D.: A survey of variants and extensions of the resource-constrained project scheduling problem. Eur. J. Oper. Res. 207(1), 1–14 (2010)
-
Havur, G., Cabanillas, C.: History-aware dynamic process fragmentation for risk-aware resource allocation. In: OTM. LNCS, vol. 11877, pp. 533–551 (2019)
-
Kellenbrink, C., Helber, S.: Scheduling resource-constrained projects with a flexible project structure. Eur. J. Oper. Res. 246(2), 379–391 (2015)
-
Kunkler, M., Rinderle-Ma, S.: Online resource allocation to process tasks under uncertain resource availabilities. In: ICPM. pp. 137–144. IEEE (2024)
-
Kunkler, M., Schumann, F., Rinderle-Ma, S.: Business process optimization: A systematic review of combining concepts from business process management and operations research. In: EDOC. LNCS, vol. 16213, pp. 61–83 (2025)
-
Leemans, S.J.J., Fahland, D., van der Aalst, W.M.P.: Discovering block-structured process models from event logs - A constructive approach. In: PETRI NETS 2013. LNCS, vol. 7927, pp. 311–329 (2013)
-
Middelhuis, J., Bianco, R.L., Sherzer, E., Bukhsh, Z.A., Adan, I., Dijkman, R.M.: Learning policies for resource allocation in business processes. Inf. Syst. 128, 102492 (2025)
-
Schumann, F., Rinderle-Ma, S.: Optimizing resource-driven process configuration through genetic algorithms. In: BPM. LNCS, vol. 14940, pp. 3–20 (2024)
-
Vanhatalo, J., Völzer, H., Leymann, F.: Faster and more focused control-flow analysis for business process models through SESE decomposition. In: ICSOC. pp. 43–55 (2007)