arXiv:2609.05578cs.AISep 2026

Manuscript Offprint

arXiv:2609.05578

Planning and Scheduling Business Processes under Control-Flow Uncertainty

Michel Kunkler, Stefanie Rinderle-Ma

Michel Kunkler[0000-0002-1920-7322], Stefanie Rinderle-Ma[0000-0001-5656-6108]

Technical University of Munich, Germany TUM School of Computation, Information, and Technology {michel.kunkler,stefanie.rinderle-ma}@tum.de

Abstract. Scheduling activities in business processes can improve efficiency (e.g., reduce makespan), but is challenging because the exact sequence of activities required to complete a case is often uncertain due to decisions based on data that emerges during execution. Nevertheless, probabilistic information regarding such decisions can often be estimated or derived from historical execution logs, and can help anticipate which execution paths are likely to lead to successful completion. Planning with particular execution paths affects feasibility, i.e., the probability of successful completion, and the expected number of superfluous activities that are planned but never executed. We frame the problem as a chance-constrained optimization problem and present two formulations: A decomposed approach with two stages, a planning stage that minimizes the expected number of superfluous activities subject to a feasibility constraint, and a scheduling stage that minimizes the makespan over the planned activities; and an integrated approach that combines planning and scheduling into a single formulation. Evaluation on two real-world and one synthetic dataset shows that the integrated approach yields superior makespans but is intractable at scale, while the decomposed approach scales to large settings.

Keywords: Business Processes · Chance Constraints · Scheduling

1 Introduction

Scheduling the execution of activities in business processes can improve operational efficiency, e.g., by reducing the makespan of cases and improving resource utilization. Moreover, schedules provide visibility into the future, which can help resources prepare for their upcoming activities and identify capacity bottlenecks, thereby supporting management decisions regarding business process improvements [3]. Formalizing and solving an optimization problem for scheduling the execution of business process activities is challenging for several reasons: high computational complexity, modeling complexity from control-flow or resource constraints, and the degree of uncertainty in business process execution [10]. Current work on scheduling activities of business processes has primarily addressed setting up computationally tractable optimization models and capturing

M. Kunkler, S. Rinderle-Ma

a rich set of control-flow and resource constraints [1,13], or addressed uncertain activity durations [7] and resource availability [9,12].

A key driver of uncertainty in business process execution is that the sequence of activities required to successfully complete a case is often not known with certainty beforehand, e.g., due to runtime constraints or decisions based on data revealed during execution. Consequently, the exact set of activities that must be scheduled for a case is not known in advance. While this issue has been acknowledged [10,7] and termed control-flow induced uncertainty [10], existing work has either focused on scheduling only until the course of the business process can be determined with high certainty [7] or adopted online resource allocation approaches [9,12]. Both strategies undermine some of the benefits of scheduling, e.g., by preventing resources from preparing for their upcoming activities.

In this work, we address the problem of planning and scheduling the activities of cases under control-flow induced uncertainty until case completion. We assume that a schedule for a case is feasible if the scheduled activities are sufficient to complete it. Moreover, we assume that any unnecessarily scheduled activity can be skipped. We refer to such activities as superfluous. The key idea of this work is to formulate activity selection as a chance-constrained optimization problem, in which activities are selected such that a predefined case feasibility threshold is satisfied while minimizing an optimization objective. We present two approaches. In the i) decomposed approach, we first determine the set of activities to be scheduled by solving a planning problem that minimizes the expected number of superfluous activities subject to a feasibility constraint; in the second step, the planned activities are scheduled to minimize the makespan, i.e., the completion time of the final activity. In the ii) integrated approach, planning and scheduling are combined into a single formulation that directly minimizes the makespan subject to a feasibility constraint. The decomposed approach allows exclusive activities to overlap, since at most one will actually execute. The integrated approach also allows non-exclusive activities to overlap, which can be beneficial when their joint execution probability is low, keeping the impact on feasibility minor.

An exemplary business process with control-flow uncertainty is shown in Fig. 1. It depicts a repair center with an exclusive choice (with two branches and their branching probabilities p1,1p_{1,1} and p1,2p_{1,2}) and a loop (with redo probability q1q_1). Below the process model, an example schedule is shown for two cases and three resources (one per swim lane). In this schedule, the Repair and Quality Control (QC) activities are planned twice for each case. Since the probability that both cases require a second loop iteration is low, these activities are scheduled to overlap, which can be achieved by the proposed integrated approach.

We formalize both approaches, provide constraint programming implementations and evaluate them on two real-world and one synthetic dataset. The results show that the integrated approach yields superior makespans but is intractable at scale, while the decomposed approach scales to large settings.

Figure

Fig. 1. Exemplary schedule for two cases with overbooking of unlikely activities with a feasibility of pcf≈0.9295p_{cf} \approx 0.9295 and an expected number of feasible cases Efc≈1.9283\mathbb{E}_{fc} \approx 1.9283.

The remainder of this paper is structured as follows. Sects. 2 and 3 present the decomposed and integrated approaches, respectively. Sect. 4 evaluates both approaches, Sect. 5 discusses related work, and Sect. 6 concludes.