Abstract

Delivered-cost estimates are often used as proxies for hydrogen import prices. Yet they measure average supply-chain costs, whereas marginal prices measure the system value of an additional unit. Market interactions can make the two diverge, potentially biasing long-term price assumptions. We quantify this gap using an 81-region global hydrogen-market model, comparing each region’s costs and prices when only its demand is active and when all regions’ demands are active. The 2045 price–cost gap is positive in 78 regions and averages 63 EUR/MWh (52% of the single-buyer cost) on a demand-weighted basis. Only 12 EUR/MWh reflects higher average sourcing costs due to competing demand. The remaining 51 EUR/MWh is the difference between the global-market price and the delivered portfolio’s average cost. In several regions, wholesale prices rise while average delivered costs fall. Hydrogen strategies should distinguish delivered-cost benchmarks from market-price expectations, as low-cost supply does not guarantee low regional market prices.

Introduction

Many governments see low-carbon hydrogen as an important option for defossilising hard-to-electrify sectors, and national hydrogen strategies often anticipate substantial imports from regions with low production costs [1, 2, 3, 4]. Progress has nevertheless fallen short of announced ambitions [5, 6, 7]. Uncertainty about future demand and prices remains an important barrier to long-term offtake agreements and investment [5, 8]. Because projected hydrogen demand responds strongly to assumed prices, expectations of future prices are central to these decisions [9, 10]. Yet few studies estimate future regional market prices [11, 12, 13, 14, 15]. Many published studies instead report production or delivered costs [16, 17, 18, 19], and these estimates vary widely. For Europe in 2050, they differ by approximately a factor of five [17]. The practical question is therefore not only where hydrogen can be produced and delivered at low cost, but also what price a region may face for the volumes it requires.

These delivered-cost estimates generally come from route-level supply-chain studies [16, 17, 18, 19]. They typically combine the levelised cost of producing hydrogen at a specified location with the costs of conversion, storage and transport along a particular route, at an assumed scale and utilisation rate. By themselves, however, these estimates do not show what price may emerge when several suppliers and buyers interact. Cost-derived assumptions are nevertheless used as regional import-price inputs in energy-system models that do not represent market prices endogenously [20, 21, 22, 23], and some national strategies use supply-cost targets as planning benchmarks [4].

Using delivered costs as price proxies may be reasonable when low-cost production and transport remain plentiful at the required volume, so that average delivered cost remains close to the marginal value of supplying the region. Global assessments suggest that low-cost production potential exceeds projected demand by a wide margin [24], although much of it lies away from demand centres and is constrained by water, land and renewable electricity availability [25]. Production potential available at a given cost is not the same as supply delivered to a region at that cost, once transport and demand elsewhere are taken into account. A region facing no competing demand from other regions uses the cheapest supply options first and turns to more expensive ones as demand increases. The average cost of its supply portfolio can therefore remain below the marginal value of supplying an additional unit, creating a price–cost gap even when the region is the only buyer. When other regions also demand hydrogen, they draw on the same finite production resources and transport routes. This can change both the average cost of the supply reaching a region and its marginal price. A region may even receive a cheaper average portfolio while facing a higher price.

The supply-chain studies discussed above represent demand only for the region they investigate, or not at all [26]. Integrated hydrogen-market models instead determine production, trade and infrastructure jointly. Many report traded volumes, routes and delivered costs without calculating regional prices [27, 28, 29]. Where regional prices are derived, they are used to interpret outcomes across scenarios, market structure or trade regimes [11, 12, 14, 13, 15]. To our knowledge, these prices have not been compared against the delivered cost of the supply reaching each region. We therefore ask how large the resulting price–cost gap is, how competing demand changes prices, and whether the gap mainly reflects a change in sourcing or prices above average delivered costs.

We address these questions using HyPriM [30], a global hydrogen-market optimisation model covering 81 regions from 2030 to 2050, building on [31]. For each focal region, we compare two matched configurations. In the single-buyer configuration, only the focal region’s prescribed demand is active, but all modelled production potentials and transport options remain available. This extends the cost logic of route studies to the region’s full demand, rather than replicating an individual study. In the global-market configuration, all regions have active demand and can produce and trade simultaneously. The focal region’s demand and techno-economic assumptions are unchanged, while investment, production and trade respond endogenously. In both configurations, we calculate the volume-weighted average delivered cost and the dual value of the regional hydrogen balance in the fixed-capacity pricing stage. We report the latter as a modelled long-run wholesale price conditional on the installed capacities and price-taking behaviour [32, 33]. The resulting four quantities allow two decompositions of the price–cost gap (Fig. 1). One separates the single-buyer price–cost difference from the price effect of competing demand. The other separates the sourcing effect, the change in average delivered cost, from the global-market price–cost difference. We examine supply changes for Germany and Japan in more detail. Germany has many pipeline options within Europe, whereas Japan has few pipeline options and can import from many potential suppliers only by ship. We find that modelled global-market prices exceed the matched cost benchmark in nearly all regions. On a demand-weighted basis, most of this difference reflects prices above average delivered costs rather than a more expensive supply portfolio. Delivered costs therefore remain useful for comparing supply options but should not be used directly as long-term price assumptions in hydrogen strategies and energy-system models.

Figure 1: Matched model configurations and decomposition of the hydrogen price–cost gap. (a) In the single-buyer configuration, only the focal region has active hydrogen demand, while the full set of global production resources and transport options remains available. Repeating the model for each focal region produces 81 matched single-buyer runs. (b) In the global-market configuration, all 81 regions have active demand and can produce and trade hydrogen in a single run. The focal region’s demand and all techno-economic assumptions are unchanged between configurations, while investment, production and trade respond endogenously. (c) Schematic cost-ordered supply blocks show the hydrogen portfolio delivered to the same focal-region demand in each configuration. The quantities c1c_{1} and cNc_{N} are the volume-weighted average delivered costs in the single-buyer and global-market configurations, respectively. The quantities p1p_{1} and pNp_{N} are the dual values of the regional hydrogen-balance constraint in the fixed-capacity pricing stage and are reported as modelled wholesale prices. These prices reflect marginal system values and should not necessarily be interpreted as the cost of the most expensive displayed supply block. (d) The price–cost gap, Γ=pN−c1\Gamma=p_{N}-c_{1}, can be decomposed along two paths. The first gives Γ=Δ1pc+Δp\Gamma=\Delta^{pc}_{1}+\Delta p, where Δ1pc=p1−c1\Delta^{pc}_{1}=p_{1}-c_{1} is the single-buyer price–cost difference and Δp=pN−p1\Delta p=p_{N}-p_{1} is the price effect of competing demand. The second gives Γ=Δc+ΔNpc\Gamma=\Delta c+\Delta^{pc}_{N}, where Δc=cN−c1\Delta c=c_{N}-c_{1} is the sourcing effect of competing demand and ΔNpc=pN−cN\Delta^{pc}_{N}=p_{N}-c_{N} is the global-market price–cost difference. The maps and supply blocks are schematic and contain no numerical results. For readability, year and region subscripts are omitted from the notation in the main text and this figure. The Supplementary Information uses the full notation, for example (pN,y,i)(p_{N,y,i}).