We study the power of migration in preemptive scheduling on identical parallel machines with time windows. If an instance admits a migratory schedule on mm machines, how many machines are needed to schedule it without migration? Kalyanasundaram and Pruhs (2001) showed that 6m−56m-5 machines suffice and gave a polynomial-time construction using 12m−512m-5 machines, whereas 2m−12m-1 machines may be necessary. We close this gap, which has been open for more than 25 years: 2m−12m-1 machines always suffice, and a corresponding non-migratory schedule can be computed in strongly polynomial time.

Our proof has two main technical ingredients. First, we introduce supercanonical schedules and prove that the conflict graph of every such schedule on mm machines is (2m−1)(2m-1)-colorable. The key property is that whenever a job pauses, the jobs running alongside it just before and just after the pause separate the jobs processed entirely during the pause from the rest of the conflict graph. We use these separators and Kempe exchanges to compute a coloring in polynomial time. Second, we construct a supercanonical schedule with polynomially many processing blocks by shrinking job windows as far as possible while preserving feasibility and solving a min-cost flow problem.

1 Introduction

In preemptive scheduling on parallel machines, a natural source of flexibility is migration: an interrupted job may resume on a different machine. Migration can make it easier to meet deadlines, but in practice it incurs communication and synchronization overhead. This raises a question: how much does migration actually help?

We study this question for scheduling jobs with time windows on identical parallel machines, in the offline setting where all jobs are known in advance. Each job has a processing time and must be processed entirely within its time window, given by a release date and a deadline. Jobs may be preempted, that is, their processing may be interrupted and resumed later, but no job may run on two machines simultaneously. A schedule is migratory if a preempted job may resume processing on a different machine, whereas in a non-migratory schedule each job is processed entirely on one machine. The power of migration measures how much the number of machines needed for a feasible schedule can increase when migration is disallowed. More precisely, for a given mm, we ask for the smallest number of machines sufficient to schedule without migration any job set that admits a feasible migratory schedule on mm machines.

Kalyanasundaram and Pruhs [13] showed that the power of migration is constant: every instance feasible with migration on mm machines admits a non-migratory schedule on 6m−56m-5 machines. Their constructive proof yields a pseudopolynomial-time algorithm, and they also give a polynomial-time

*Faculty of Mathematics and Computer Science, University of Bremen, Germany. Email: {nicole.megow,bart.zondervan}@uni-bremen.de This work was supported by supported by the Deutsche Forschungsgemeinschaft (DFG, German Research Foundation) grant no. 517912373 and under Germany's Excellence Strategy – EXC 3036 The Martian Mindset – project number 533607631.

algorithm using 12m−512m-5 machines. Conversely, a simple instance with identical release dates and deadlines shows that 2m−12m-1 machines may be necessary [16].

In this paper, we close this gap, which has been open for more than 25 years, by proving that 2m−12m-1 machines always suffice and constructing such a non-migratory schedule in strongly polynomial time.