Approximation and Hardness for the Data Validation Problem

Antoine Tinguely, G. Wessel van der Heijden

Open access. PaperVantage converted this article to text, so layout and figures may differ from the original.

Abstract

In scheduling, precedence constraints stipulate that certain tasks can only be scheduled after the completion of other tasks, and have been studied extensively in theory and applications. In many practical cases, some presumed precedences are redundant, so it can be beneficial to invest some resources to challenge the validity of such constraints. If a constraint turns out to be unnecessary, discarding it can drastically improve the optimum of the scheduling instance.

To model such scenarios, Finnah, Gönsch and Otto [Eur. J. Oper. Res. 2025] recently introduced the Data Validation Problem (DVP): Given a transitive directed acyclic graph GG on nn vertices (resp. tasks) and mm edges (resp. precedences) and a probing budget, a policy can successively pay a probing fee and probe an edge in GG as long as the total probing fees do not exceed the budget. If a probe succeeds, the targeted edge ee is removed from GG and we receive a reward; if the probe fails, the edge stays in GG and cannot be probed again. We seek a policy with maximum expected cumulative reward. Crucially, GG must stay transitive throughout the probing process, so a policy can only challenge the precedence between consecutive tasks, that is, only probe edges in the transitive reduction of the current precedence graph.

While DVP has been explored using heuristic methods, little is known about the worst-case complexity and approximability of the problem. We initiate the theoretical study of DVP by proving that DVP is strongly NP-hard and W[1]-hard with the probing budget TT as a parameter, even in the deterministic case (when every probe has probability 0 or 1 to succeed) and with unit probing costs and rewards. For the same setting, we give an approximation-preserving reduction from the Densest kk-Subgraph (DkS) Problem, with the consequence that there is no polynomial-time 2(log⁡n)1−δ2^{(\log n)^{1-\delta}}-approximation algorithm and no FPT T\sqrt{T}-approximation algorithm for DVP, assuming the Almost-Exponential Time Hypothesis and the Strongish Planted Clique Hypothesis, respectively.

We also present the first known policies with provable worst-case guarantees for DVP, namely an mm-approximation algorithm for instances with uniform probabilities and probing costs, a 2T/pmin⁡T2T/p_{\min}^{T}-approximation algorithm for general instances, where pmin⁡p_{\min} is the minimum probing success probability, and an exact FPT algorithm on tournament graphs, in the deterministic setting.

1 Introduction

Scheduling under precedence constraints is a classic topic in theoretical computer science and operations research. In a precedence-constrained scheduling instance, a set of tasks is given together with a partial order ≺\prec, which is the set of precedence constraints. The partial order can also be encoded as a so-called precedence graph. Given two tasks t,t′t, t', whenever t≺t′t \prec t', task tt must be completed before task t′t' can start. Tasks that are incomparable in the partial order ≺\prec may be processed in any order. The focus of the literature for scheduling with precedence constraints has considered the partial order as an input and has been primarily focused on scheduling tasks according to some objective function depending on when tasks are assigned on a time line. Many variations of precedence constraints have been studied, where the structure of the partial order ≺\prec can strongly affect both the computational complexity of the problem and the optimal objective value [PBM18]. A more basic question has received much less attention: how is the precedence structure obtained in the first place? In practice, the precedence constraints are rarely given explicitly with full confidence and must first be determined. This is a question that has been considered in the operations research community as the Data Validation Problem (DVP) introduced by Finnah, Gönsch and Otto [FGO25]. However, to the best of our knowledge, the computational complexity or approximation bounds for this problem have not been studied from a theoretical perspective. In this paper, we initiate the theoretical study of the problem of determining the precedence structure of a scheduling problem. We give complexity results and approximation guarantees for this problem and several natural variants.

We formally describe DVP following the definition in [FGO25]. We are given a probing budget T∈NT \in \mathbb{N} and a directed acyclic graph (DAG) G=(V,E)G = (V, E) which is also transitive, that is, (u,v)∈E(u, v) \in E and (v,w)∈E(v, w) \in E imply (u,w)∈E(u, w) \in E. Let n:=∣V∣n := |V| and m:=∣E∣m := |E|. Each edge e∈Ee \in E has a weight we∈N0w_e \in \mathbb{N}_0, a probing cost τe∈N0\tau_e \in \mathbb{N}_0, and a success probability pe∈[0,1]p_e \in [0,1], to which is tied a random variable Ωe∼Bernoulli(pe)\Omega_e \sim \text{Bernoulli}(p_e). We assume the random variables {Ωe}e∈E\{\Omega_e\}_{e \in E} to be (mutually) independent.

Iteratively, an (adaptive) probing policy can probe an edge e∈Ee \in E by paying τe\tau_e, i.e., by decreasing the probing budget by τe\tau_e. Then, we reveal the outcome of Ωe\Omega_e (which is unknown before the probe). If the probe succeeds, i.e., in the event that Ωe=1\Omega_e = 1, we collect wew_e as a reward, and ee is removed from EE; otherwise, if the probe fails, i.e., if Ωe=0\Omega_e = 0, we collect no reward, ee stays in EE and cannot be probed anymore. Crucially, we impose that an edge can only be probed if it lies in the transitive reduction of EE, which is the set of all edges (u,v)∈E(u, v) \in E such that E∖{(u,v)}E \setminus \{(u, v)\} contains no (directed) u−vu-v-path,1^1 which we denote by R(E)\mathcal{R}(E). The transitive reduction of GG can be computed in time O(n2.4)O(n^{2.4}) [AGU72, BJG08] statically and be updated in time O(n1.528+m)O(n^{1.528} + m) at each edge deletion [GKMP25]. The policy must halt if every edge in R(E)\mathcal{R}(E) has already been probed or if τe>T\tau_e > T for any unprobed edge e∈R(E)e \in \mathcal{R}(E). Thereby, a policy π\pi yields the expected total reward W(π):=E[∑e∈E1{π successfully probes e}]W(\pi) := \mathbb{E}\left[\sum_{e \in E} \mathbf{1}_{\{\pi \text{ successfully probes } e\}}\right], where 1C\mathbf{1}_C denotes the indicator function of an event CC; the goal is to find a policy π∗\pi^* with maximum expected reward, i.e., π∗∈arg⁡max⁡policy πW(π)\pi^* \in \arg\max_{\text{policy } \pi} W(\pi).

We remark that we allow policies to sample random variables other than {Ωe}e∈E\{\Omega_e\}_{e \in E} but that are independent of {Ωe}e∈E\{\Omega_e\}_{e \in E}. For any E′⊆EE' \subseteq E, we write τ(E′):=∑e∈E′τe\tau(E') := \sum_{e \in E'} \tau_e, w(E′):=∑e∈E′wew(E') := \sum_{e \in E'} w_e and p(E′):=∏e∈E′pep(E') := \prod_{e \in E'} p_e.

Intuitively, the assumption of only probing edges in the transitive reduction is motivated by the interpretation of GG as a precedence graph. If a precedence graph GG contains a path P=(u1,u2,…,uk)P = (u_1, u_2, \ldots, u_k), by transitivity, it also contains the edge e=(u1,uk)e = (u_1, u_k), so removing ee but no edge in PP cancels transitivity, meaning that this framework no longer models the removal of redundant precedences in a meaningful way.

Determining the precedence constraints between tasks is a problem that is often faced in practice. The problem arises in many industries with business processes subject to hard constraints such as precedence

1^1When we speak of paths on a DAG, we always mean directed paths.

constraints, including product design, assembly and manufacturing, project scheduling, construction, and logistics [FGO25, WKFB09]. In such processes, the relation between every pair of tasks is rarely documented explicitly and an expert must be consulted to determine it. Moreover, Otto and Otto [OO14] showed that probing direct precedence relations can increase the probability of being able to remove the edge in automotive assembly processes. Wang et al. [WKFB09] investigated the Assembly Sequence Problem, a problem similar to DVP, which is a well-studied problem in the operations research community. Finnah et al. [FGO25] recently expanded on the model by imposing constraints on the available expert time or cost. They showed that solving the problem, even approximately, can significantly improve business outcomes. Other questions regarding the complexity or approximation guarantees remained open.