BOLT: Multi-Bottleneck Bound-Guided Learning for Flexible Job-Shop Scheduling with Time Lags and Resource-Coupled Transport

Ziheng Zhang, Wei Zhang, Yunyi Zhao, Zuming Liu, Wei Zhou, Boon Ping Gan

Open access. PaperVantage converted this article to text, so layout and figures may differ from the original.

Ziheng Zhang, Wei Zhang, Yunyi Zhao, Zuming Liu, Wei Zhou, and Boon Ping Gan

Abstract—Flexible job-shop scheduling becomes resource-coupled when a scarce vehicle fleet moves jobs between stations, because the schedule sets the transport waits. BOLT (bound-oriented learning for transport-coupled scheduling) builds a lower bound from chain, machine-capacity, and fleet-capacity relaxations. The bound equals the makespan at termination, so its per-step changes form a reward that sums to a constant minus the makespan. Because it never exceeds the attainable makespan, each candidate's bound increase is a proven rise of the makespan floor, which the policy reads as a price. The root bound certifies a completed schedule's suboptimality gap without a solver. On industry-motivated 10-module prefabricated-construction instances, explicit transport coupling outperforms a transport-penalty policy in every tested cell where loaded moves occupy at least 66% of fleet time and in none at or below 56%. Across five zero-shot 50- and 80-module production batches, BOLT outperforms the best dispatching-rule pair on four and the penalty policy on the three with long moves. In the three-vehicle 80-module batch, its mean makespan is 13.0% below the best pair and 4.2% below an hour-budget constraint-programming solver whose proven gap averages 34%. BOLT decides in 2.3–5.9 ms per event on one processor core and re-plans a disruption in seconds.

Note to Practitioners—Many plants move heavy modules between stations on a few transporters or automated guided vehicles, and the wait for a vehicle depends on the schedule. This paper gives such a plant a dispatcher guided by a guaranteed lower bound on completion time. The dispatcher decides each machine and vehicle assignment within milliseconds on one processor core and re-plans within seconds after a breakdown. Its station and vehicle decisions have separate output layers, so a plant can retune or roll back one class while the other stays fixed. Without a solver, the dispatcher reports a guaranteed bound on each schedule's distance from optimal, which is loose on large batches (38–47% on average).

The cases studied use published process data for prefabricated prefinished volumetric construction. Only tested cases with loaded moves of 2.8 to 4.7 h, as between separate production areas or with a slow fleet, showed gains over a fixed transport allowance. In the 10-module cases, explicit transport modeling reduced makespan in every tested case where loaded trips occupied at least 66% of fleet time, and a fixed transport allowance sufficed at or below 56%. A plant estimates this share from its expected loaded travel, fleet size, and batch duration, and trains the policy once on its instance mix. At high load, the dispatcher lost to the best dispatching rules in one tested case, where one vehicle served 80 modules.

The model assumes known processing, waiting, and travel times and does not model stochastic arrivals, vehicle routing and congestion, or mixed fleets. A schedule executed under duration noise of up to ±30%\pm30\% stayed within 0.7% of re-planning. When a plant can wait minutes for a plan, per-instance search finds shorter schedules. Extending the method to stochastic arrivals and online dispatch without a reserved destination machine is the next step.

Index Terms—Automated guided vehicles, bound-guided reinforcement learning, flexible job-shop scheduling, prefabricated construction, resource-coupled transport.

I. INTRODUCTION

Automated production systems often move partly finished products between stations on a shared transporter or automated guided vehicle fleet. Their machine and vehicle schedules jointly set throughput. Prefabricated prefinished volumetric construction (PPVC) is one heavy-load case, in which factories build whole rooms before shipment to site. Singapore mandates PPVC on selected government land-sale sites, and one documented project moved 1,866 modules that each weighed 26 to 31 tons [1], [2]. Another documented development erected two 56-story towers from 3,034 such modules, about 27 modules per floor [3]. Each module rides a heavy transporter between stations, and every move occupies one vehicle for its full duration, so the plant must assign stations and vehicles together whenever a module becomes ready.

This joint decision is difficult because the schedule determines each transport wait. A job moves through a sequence of stations, with a vehicle carrying it between different locations. Some waits have durations that the instance fixes. A cast module must cure, which means harden, for a known time before the next operation can begin, and a machine setup takes a known time once the job order is chosen. Transport waits differ, because a finished module remains at its station until a vehicle becomes free, and how long that takes depends on which other jobs are using the fleet at that moment. Machine decisions set when transport requests arise, while fleet availability sets when the next operation can start. A fixed travel allowance therefore misjudges the delay when vehicles are scarce, and the scheduler must represent the load that each decision places on the fleet.

This work has been submitted to the IEEE for possible publication. Copyright may be transferred without notice, after which this version may no longer be accessible.

Z. Zhang, W. Zhang, and Y. Zhao are with the Infocomm Technology Cluster, Singapore Institute of Technology, Singapore 828608 (e-mail: ziheng.zhang@singaporetech.edu.sg; wei.zhang@singaporetech.edu.sg; yunyi.zhao@singaporetech.edu.sg).

Z. Liu is with the College of Smart Energy, Shanghai Jiao Tong University, Shanghai, China (e-mail: zmliu@sjtu.edu.cn). W. Zhou is with the School of Computer Science and Informatics, Cardiff University, Cardiff CF244AG, U.K. (e-mail: ZhouW26@cardiff.ac.uk). B. P. Gan is with D-SIMLAB Technologies, Singapore (e-mail: boonping@d-simlab.com). Corresponding author: Wei Zhang.

Existing scheduling methods do not provide that representation as a certified learning signal. Prefabrication scheduling studies omit transport or treat it as a fixed time surcharge [4], and learning studies of dynamic flexible job shops model it as a fixed transfer delay [5]. Exact and metaheuristic models schedule a finite fleet [6]–[8]. Because they search each instance separately, they do not amortize scheduling decisions into a learned millisecond-scale dispatcher. Learning-to-dispatch policies make online decisions in milliseconds [9]. Several such methods derive each reward from changes in a lower bound on the makespan attainable from the partial schedule [10]–[13]. If the bound equals the makespan at termination, these rewards sum to a constant minus the makespan, so maximizing their return minimizes makespan exactly. These bound-guided methods [10]–[13] do not model an explicit vehicle resource. Most vehicle-aware learners [14]–[16] use designed rewards or learned estimates. Moon et al. [17] combine vehicle decisions with a chain-bound reward, but their bound omits aggregate fleet capacity. A chain bound follows each job's own remaining operations with one fixed travel time per move, so it treats every job as if a vehicle were always free. It stays flat as the makespan grows with the number of jobs waiting for one vehicle. What remains missing is an admissible bound, tight at termination, that counts aggregate fleet workload, so that an objective-faithful reward also responds to fleet contention.

The principle adopted here is to represent every shared bottleneck in one admissible bound. For each partial schedule, chain, machine-capacity, and fleet-capacity relaxations bound job progression, machine workload, and mandatory loaded moves. Their maximum remains admissible because none can exceed the makespan attainable from that state, and it selects the active bottleneck with no tuned weight. The fleet-capacity term aggregates transport work across jobs, so it rises under contention where a chain bound stays flat. The same quantity can then connect the scheduling objective to learning decisions, certified gap bounds, and solver search.

BOLT (bound-oriented learning for transport-coupled scheduling) implements this principle with a certified multi-bottleneck lower bound. The bound is admissible at every reachable partial schedule (Section IV). It equals the makespan at termination, so its one-step change supplies an objective-faithful reward. For each candidate, the successor bound gives a certified action price, which is a proven minimum increase in the makespan lower bound (Section V). At the root, the same quantity gives a solver-free certified upper bound on the relative suboptimality gap of any completed schedule. As a redundant constraint, its fleet-capacity term also raises the lower bound that warm-started CP-SAT proves in the tested one-vehicle cells (Section VI-D3). The merged-head and factorized realizations read the same bound signals, so controller ownership does not change the learning objective. Whether that objective's fleet term changes the schedules a plant runs depends on how heavily the fleet is loaded.

On the prefabricated-construction instances tested, the benefit of explicit coupling depends on fleet load. At the 10-module training size, explicit coupling shortens makespan in every cell at or above 66% loaded utilization, and a transport-penalty policy is adequate at or below 56%. Production batches of 50 and 80 modules match the output of two to three tower floors and lie outside the trained sizes. On the three batches with long moves, BOLT outperforms this penalty policy on every instance. In the 80-module batch with three vehicles, its mean makespan is 13.0% below the best dispatching-rule pair and 4.2% below warm-started CP-SAT given an hour, whose proven gap averages 34%. Ablations on four pre-specified cells attribute the training improvement to the action-price feature. Removing the fleet-capacity term lengthens the schedules by 4.8% and 6.2% in the two 10-module cells where that term sets the bound, and by 12.9–23.0% on three production batches. BOLT takes 2.3–5.9 ms per event on one processor core, or 0.8–15.9 s for a whole schedule, from 10 to 80 modules. After a machine breakdown, it re-plans in 7–14 s, while CP-SAT at budgets of 1 and 10 s returns the right-shifted plan unchanged. A genetic algorithm needs 33–120 s to find a schedule shorter than BOLT's. Plants can use BOLT to learn and deploy resource-coupled transport scheduling, bound a completed schedule's relative suboptimality gap without a solver, and decide when explicit coupling is useful.

The scheduling model is deterministic, with processing, waiting, and travel times known before scheduling begins, and machine choice lies within a station cell, as in the PPVC layouts studied. Similar conditions arise when heavy partly finished products move on a small automated guided vehicle fleet [7], [14], [15]. The studied PPVC instances come from an industry-motivated generator whose routing classes and operation structure follow published PPVC process documentation [2]. They contain no plant's production records, and the study reports no plant deployment. Within this scope, to our knowledge, no learned flexible job-shop scheduler combines this bound with certified action pricing, a solver-free certified gap bound, and solver strengthening. Splitting control between machine and vehicle controllers is not part of this claim, because it is established practice [5], [14]–[16]. None of these systems trains on a proven bound (Section II). BOLT makes online dispatch decisions, while exact and metaheuristic methods with per-instance budgets provide solution-quality references. The paper makes four contributions.

• Resource-coupled scheduling formulation. We formalize flexible job-shop scheduling with machine-free time lags and a finite fleet whose vehicles are seized for each move and whose destination machines are reserved in transit. A delay-semantics taxonomy distinguishes resource-coupled transport from machine-free and machine-side delays (Section III).

• Certified multi-bottleneck bound. We construct a certified multi-bottleneck lower bound from chain, machine-capacity, and fleet-capacity relaxations. It is admissible at every reachable partial schedule (the machine term under the type-pure eligibility of the studied layouts), and its tightness at termination makes its one-step change an objective-faithful reward (Section IV).

• Bound-oriented learning and decision support. BOLT reuses the bound for certified action prices and a solver-free bound on the relative suboptimality gap of a completed schedule. Its fleet term also acts as a redundant constraint that raises the lower bound CP-SAT proves in the tested one-vehicle cells (Sections V, VI).

  • Operating regime and deployment. On the training-size grid, explicit coupling shortens makespan in every cell at or above 66%66\% loaded utilization, whereas a transport penalty is adequate at or below 56%56\%, so the tested crossover lies between these values. Across five 50- and 80-module production batches outside the trained sizes, the policy outperforms the best dispatching-rule pair on four and loses by 1.5%1.5\% where one vehicle serves 80 modules. Its factorized realization costs up to 4.4%4.4\% in makespan there against one merged head, gives the station and vehicle controllers separate decision layers, and dispatches in milliseconds (Section VI).