arXiv:2610.20070cs.NIOct 2026

Manuscript Offprint

arXiv:2610.20070

SPARC: Substation-to-Peering Assessment of Resilience and Cascades

Tanya Shreedhar, Kevin Vermeulen, Amreesh Phokeer, Italo Cunha, Fernando Kuipers

Open access. PaperVantage converted this article to text, so layout and figures may differ from the original.

TANYA SHREEDHAR, TU Delft, The Netherlands

KEVIN VERMEULEN, LIX, CNRS, Ecole Polytechnique, France

AMREESH PHOKEER, Internet Society, USA

ITALO CUNHA, Universidade Federal de Minas Gerais, Brazil

FERNANDO KUIPERS, Delft University of Technology (TU Delft), The Netherlands

Internet Exchange Points (IXPs), where networks exchange a large share of Internet traffic, operate from colocation facilities that draw power from the regional grid and store a limited supply of backup fuel. In April 2025, the Iberian blackout kept the Spanish grid down for 16 hours, longer than the 12 hours of fuel that the industry standard requires, and traffic at major Iberian IXPs fell by up to 70%. Yet operators cannot tell which facilities such an event cuts off, whether the outage outlasts their backup, or where the traffic of a failed IXP goes. Prior work leaves these questions open, as it maps the grid dependency of the Internet only at the scale of whole synchronous grids or detects outages after they happen. We present SPARC, to our knowledge the first study that maps the interdependence of the power grid and Internet infrastructure from the substation to the IXP and to its traffic. SPARC extracts the high-voltage substations from open data, checks them against the registries of transmission operators, and links each facility to the substations that likely feed it, creating a bird's-eye view of the substations on which 552 facilities and 275 IXPs depend. To understand which IXPs a grid event takes offline and where their traffic goes, we spread grid events over this map and measure failover with controlled BGP withdrawals on the PEERING testbed. We find that the dependency of European IXPs is concentrated, as disabling the most-shared 16% of the substations that feed facilities cuts power to half of all IXP presences (an IXP at one facility), under half of what randomized maps require. A grid event also reaches far beyond the substations it strikes, since losing the 5% most central substations cuts power to 0.1% of IXP presences directly but to 9–52% once the grid splits into disconnected islands. Because traffic fails over mostly to nearby sites, which often share the failing grid, a cascade that takes down four metropolitan areas at once sends up to 40% of the monitored addresses of one area to another of the four. Building on these findings, we design SPARC-SHIELD, which strengthens IXPs against grid events by selecting the substations to harden or the facilities whose backup to extend. Against an attacker who disables ten substations, hardening the ten that SPARC-SHIELD selects cuts the IXP presence offline by 72%, 1.4× the 52% of the best standard ranking.

1 Introduction

On 28 April 2025, the Iberian Peninsula lost its entire power supply [1]. An overvoltage in southern Spain tripped generation, and the loss of generation cascaded through the grid until the peninsula separated from the rest of the European grid [1]. Data centers in Spain and Portugal switched to backup power and stayed in operation [2], yet traffic at four major Iberian Internet Exchange Points (IXPs) still dropped by 33–70%, and the disruption reached networks in Morocco and Angola through transit dependencies [3]. The grid returned after 12 hours in Portugal and 16 hours in Spain [1], longer than the 12 hours of fuel that the industry standard requires a data center to store [4]. Without refueling, a Spanish facility with only the required fuel would therefore have gone offline 4 hours before the grid returned.

Authors' Contact Information: Tanya Shreedhar, t.shreedhar@tudelft.nl, TU Delft, The Netherlands; Kevin Vermeulen, kevinmylinh.vermeulen@gmail.com, LIX, CNRS, Ecole Polytechnique, France; Amreesh Phokeer, phokeer@isoc.org, Internet Society, USA; Italo Cunha, cunha@dcc.ufmg.br, Universidade Federal de Minas Gerais, Brazil; Fernando Kuipers, f.a.kuipers@tudelft.nl, Delft University of Technology (TU Delft), The Netherlands.

Shreedhar et al.

This chain from the grid to the Internet starts with a fault at a few substations, which can spread through the transmission grid until whole regions lose power. Each colocation facility 1^{1} in such a region draws its power from nearby high-voltage substations, its feeders, and falls back on batteries and generators when they fail [5]. Because an IXP operates from one or several facilities, and one facility often hosts several IXPs [6], the loss of one building can affect several exchanges at once. As the facilities of an IXP run out of backup power, its members are disconnected, and BGP moves their traffic to other sites where the same networks interconnect. That traffic survives only if those sites do not depend on the same failing grid.

The interdependence between the power grid and Internet infrastructure remains unmeasured, because the data and the communities that study the two domains sit apart. Transmission operators publish their grids in different forms or not at all, the substation that feeds a facility is a private arrangement between the facility and its grid operator, and Internet facilities appear only in operator-maintained registries such as PeeringDB [7]. Power-systems research models cascades inside the grid [8, 9], while Internet measurement detects IXP outages at the network layer after they happen, without the grid event behind them [10, 11]. The closest work maps power and Internet infrastructure at the scale of whole synchronous grids [12], a scale at which an event inside one synchronous area, such as the Iberian blackout, is not visible.

The open question is not whether the Internet depends on the grid, but which IXPs a grid event takes down, after how long, and where their traffic goes. We answer it with SPARC, to our knowledge the first study that maps the interdependence of the power grid and Internet infrastructure from the substation to the IXP and to its traffic. We first map Europe’s high-voltage substations from OpenStreetMap [13], link each IXP facility to its nearest substations, and check both against the registries of two transmission operators in the region [14, 15]. To observe where traffic goes, we then emulate the loss of IXP sites in the real Internet with BGP withdrawals on the PEERING testbed [16]. Finally, we spread grid events over the measured map and compare their duration with facility backup. Building on these findings, we design SPARC-SHIELD, which selects the substations or facilities to harden so that grid events take the least IXP presence offline.

We organize the study around four questions. RQ1\boxed{RQ1} Which substations power Europe’s IXPs, and how concentrated is this dependence? RQ2\boxed{RQ2} When the IXP facilities of a metropolitan area lose power, where does their traffic go, and does it reach sites on the same grid? RQ3\boxed{RQ3} How much IXP presence does a grid event cut off as it spreads, and when does the outage outlast facility backup? RQ4\boxed{RQ4} Which substations or facilities should an operator harden to prevent the most IXP outages, and how much does that choice depend on the threat? Our contributions are fourfold.

RQ1 A substation-level map of the grid-Internet dependency in Europe. We extract 20,085 high-voltage substations in the scope 2^{2} from OpenStreetMap, connect them along the transmission lines, and link each of 552 PeeringDB facilities, which host 275 IXPs, to its three nearest substations as candidate feeders. To our knowledge, this is the first map of this dependency at substation granularity across a continent. Against the ground-truth registries of the Dutch and French transmission operators, the map recovers 98.1% and 96.7% of the substations at a precision of 86.2% and 98.5%, and the candidate feeders contain the feeder that Dutch network operators publish [17] for 58 of 61 facilities (§3). We measure how concentrated the dependency is by the number of substations that

1^{1}A facility is a building that hosts networking equipment and draws power from the grid. An IXP is a layer-two switching fabric on which networks exchange traffic. It may span several facilities, and a facility may host several IXPs. An IXP presence is one IXP at one facility.

2^{2}Albania, Austria, Belgium, Bosnia and Herzegovina, Bulgaria, Croatia, Czechia, Denmark, Estonia, Finland, France, Germany, Greece, Hungary, Italy, Latvia, Liechtenstein, Lithuania, Luxembourg, Moldova, Montenegro, the Netherlands, North Macedonia, Norway, Poland, Portugal, Romania, Serbia, Slovakia, Slovenia, Spain, Sweden, Switzerland, and Ukraine, i.e., the Continental European and Nordic synchronous areas. Montenegro has no PeeringDB facility and no facility-level result.

must fail before half of European IXP presence loses power. When the most-shared substations fail first, 16.2% of those that feed a facility suffice, whereas maps with the IXP presences shuffled or the candidates rewired need 2.1−2.4×2.1-2.4\times as many ( §5.1\S5.1).

RQ2 Controlled measurements of IXP-site failover. We withdraw prefixes from PEERING sites one at a time and in cascades, and observe for 404,957 addresses in 61,061 ASes where their traffic is rerouted. Most traffic moves to the nearest sites, which in Europe often share the grid of the failed site. Some traffic, however, moves thousands of kilometers, because regional transit providers deliver it at distant sites ( §4§4).

RQ3 Analysis of how far grid events reach. We spread grid events over the measured map. Because whether an island keeps power after a split depends on its balance of generation and load at that moment, we bound island survival with two rules, one matching the 2006 split and one the 2003 and 2025 splits. Propagation causes most of the outage, as losing the 5% most central substations cuts power to 0.1% of IXP presence directly but to 8.8–51.7% once the grid splits, between the two rules. With 12 hours of fuel and no refueling, only events longer than 12 hours take IXP presence offline, and the 2003 Italian and 2025 Iberian blackouts both lasted longer. When a grid cascade takes down four metropolitan areas, 7–40% of the monitored addresses of each fail over on PEERING to another of the four before reaching a working site ( §5§5, §6.2§6.2).

RQ4 SPARC-SHIELD, hardening built on the measured dependency. An operator can harden a limited number of substations, for example with pre-positioned mobile generators [18], or extend the backup of a limited number of facilities. SPARC-SHIELD chooses them against grid cascades and against an adversary who disables a few substations, as in documented physical attacks (Table 6, Appendix B.2), following the defender-attacker formulation of infrastructure protection [19]. Against an adversary who disables ten substations, hardening the ten that SPARC-SHIELD selects lowers the IXP presence offline from 167 to 47, whereas the best standard ranking leaves 80, 1.7× as much. The best set also changes with the threat that the operator plans for (§6).

To support reproducibility, we will release our dataset and analysis code upon acceptance.