Forecast lead time and the timing of crew deployment for weather-driven power outages using AI weather models

Mohammad Kian Golkar, Luciano Alves de Oliveira, Mohamad Alipour

Open access. PaperVantage converted this article to text, so layout and figures may differ from the original.

ABSTRACT

Utilities request mutual aid crews to restore power after severe storms, and requesting early secures more crews but relies on less accurate forecasts. We examined how forecast lead time affects the value of outage predictions for crew deployment, using operational forecasts from two AI weather models, GraphCast and FourCastNet, to predict outage occurrence for counties across the contiguous United States 24 to 120 hours ahead. Forecasts were evaluated by the share of outage burden captured by the counties where crews would be staged. Captured burden declined with lead time: the loss between three and five days was significant in all analyses, whereas the loss within three days was significant only for outages that had not yet started. Early deployment with all requested crews outperformed late deployment with fewer, and we report the availability ratio at which the two break even. Antecedent land surface predictors computed at forecast valid time include weather from the forecast period, which inflates their skill by 42 to 53% and reverses their apparent advantage over forecast meteorology at long lead times. Computed correctly, they improved occurrence skill by 17.5% at 24 hours but did not significantly change captured burden, a gap that attribution analysis linked to their static component. Prediction intervals covered only 0.476 of tropical cyclone events against a nominal 0.90. Calibration by hazard class corrected most of this shortfall at an 11% cost in interval width, as a diagnostic only, because hazard class is known only after the event.

Keywords Power outages · AI weather forecasting · Crew deployment · Outage prediction · Conformal prediction · Data leakage

1. Introduction

Power outages caused by severe weather lead to large economic and social losses, and their duration, frequency and magnitude have increased in recent years (Ma et al., 2025). Outages linked to climate hazards are widespread across the United States and affect socially vulnerable communities more than others (Do et al., 2023; Flores et al., 2024; Ganz et al., 2023). Their consequences include disrupted medical care and exposure to extreme heat and cold (Andresen et al., 2023), which makes the resilience of power systems under climate change an important concern (Panteli and Mancarella, 2015; Ptak et al., 2025). Recent studies have also shown that hardening the most critical circuits can improve this resilience (Stürmer et al., 2024).

Before a forecast storm, utilities position restoration crews in the areas expected to be affected (Guikema et al., 2014). For large events, they also request additional crews and restoration material from other utilities through mutual assistance agreements (Zhai et al., 2021). This is a costly decision, which can reach tens of millions of dollars per day for large utilities (Zhai et al., 2021). Crews must travel from other regions and be staged at specific locations in advance, so the decision fixes both the number of crews and their locations. Previous studies have optimised the dispatch of repair crews after an event together with network reconfiguration and mobile generation (Lei et al., 2019), and the staging of resources before hurricanes under uncertain scenarios (Arab et al., 2015). However, these studies take the forecast as given. The question of when the forecast is accurate enough to commit crews has not been studied as a decision in its own right. Requesting crews early secures them before other utilities do, but the allocation is based on a forecast several days ahead. Requesting late provides a better forecast, but the available crews may already be committed elsewhere. Both effects can be measured. Forecast quality at each lead time can be compared with observed outages, and the value of an allocation can be measured as the share of observed outage burden in the counties where crews were placed. Identifying the lead time at which forecast errors start to outweigh the benefit of early commitment would give utilities a quantitative basis for a decision that is currently based on convention.

Many statistical and machine learning models have been developed to predict weather-related outages. Most combine numerical weather prediction output with information on vegetation, infrastructure and the local environment. For distribution networks, these include decision tree and ensemble methods (Wanik et al., 2015; He et al., 2017; Cerrai et al., 2019; Watson et al., 2022), quantification of uncertainty in model training (Yang et al., 2020), hybrid models that combine physics and data for infrastructure hardening (Hughes et al., 2022), and, more recently, graph neural networks and methods for rare events (Shen et al., 2026; Azizi et al., 2026). For hurricanes, generalised additive and tree models have been used to estimate damage before landfall (Han et al., 2009; Guikema et al., 2010), to handle the large number of areas with zero outages (Guikema and Quiring, 2012), and to include soil, elevation and other local factors (McRoberts et al., 2018). Nateghi et al. (2014) showed that simpler models often perform as well as more complex ones. Similar models have been developed for extratropical storms in Europe (Tervo et al., 2021), and synthetic distribution systems have been used to predict outages where outage records are not available (Zhai et al., 2021).

These models have been useful in practice, but they share two limitations. First, they are trained on outage records from one utility or a small group of utilities, so they cover a service territory rather than a whole country. Second, their weather inputs come from conventional numerical weather prediction, usually the Weather Research and Forecasting model, or from reanalysis. The public release of the Environment for Analysis of Geo-Located Energy Information (EAGLE-I) outage record (Brelsford et al., 2024; Tansakul et al., 2023) has addressed the first limitation. This record has been used for national analysis of outages (Do et al., 2023), vulnerability indexing (Ma et al., 2025), prediction at state and regional scale (Fatehi et al., 2025), and data infrastructure that links outages to other geospatial data (Frakes et al., 2026). The second limitation remains, although weather forecasting itself has changed considerably in recent years.

Weather forecasting has changed rapidly in recent years with the development of AI models that are trained on reanalysis data instead of solving the equations of atmospheric motion. GraphCast produces forecasts up to ten days ahead that are competitive with operational systems for many variables (Lam et al., 2023). Pangu-Weather achieves similar results with a 3D transformer (Bi et al., 2023), and FourCastNet uses Fourier neural operators to forecast at high resolution (Pathak et al., 2022). Probabilistic models based on diffusion (Price et al., 2025) and general Earth system models (Bodnar et al., 2025) have followed, and archives of their forecasts are now available for community evaluation (Radford et al., 2025). However, the use of these forecasts for impact prediction has received much less attention than their meteorological evaluation. This matters because AI forecasts differ from conventional ones in ways that affect impact models. They smooth weather fields and weaken extremes as lead time increases, and they show systematic biases in tropical cyclone intensity (DeMaria et al., 2025). Charlton-Perez et al. (2024) found that they capture the overall structure of storms but underestimate peak wind speeds. Both properties affect damage prediction, because damage increases sharply with wind speed.

Several studies have examined how weather forecast errors propagate into outage predictions, but only for conventional forecasts. Yang et al. (2021) quantified how forecast uncertainty at lead times of one to five days affects outage prediction error. They found that the error depended weakly on lead time up to three days and increased stepwise at four and five days. Esmaeilian et al. (2026) examined error propagation under forecast, analysis and operational scenarios.

These studies show that the question can be answered for conventional forecasts at the scale of a single utility. In this study, we address it for AI forecasts at national scale and extend it to an operational decision.

Other studies have shown that outage risk at a given wind speed also depends on the state of the land surface before the storm. Saturated soil weakens root anchorage and makes trees easier to uproot, trees in leaf catch more wind than bare trees, and snow adds load to power lines and branches. Manning et al. (2025) found for windstorms in the United Kingdom that high antecedent rainfall and summer foliage increase outage probability at a given wind speed, and that ignoring these factors can underestimate the probability of large outages by a factor of two to five. In North America, soil and elevation characteristics (Quiring et al., 2011; McRoberts et al., 2018) and vegetation (Cerrai et al., 2019) have also improved outage models. These land surface predictors are attractive for forecasting because they describe conditions that already exist when the forecast is issued. They may therefore remain informative as weather forecasts become less accurate at longer lead times, and this expectation can be tested.

However, these predictors also carry a methodological risk. Antecedent conditions are usually computed over a rolling window. If this window ends at the time the prediction is valid for, rather than the time the forecast is issued, it includes weather that occurs during the forecast period. This happens whenever reanalysis data are joined to the outage target on a shared time index, and it produces no error or warning. The resulting predictor then partly observes the storm being predicted instead of describing conditions before it, and this contamination increases with lead time. This is a form of data leakage, which Kapoor and Narayanan (2023) showed is common in scientific studies that use machine learning and inflates their reported performance. To our knowledge, it has not been quantified for antecedent predictors in impact forecasting.

This study links an operational archive of AI weather forecasts to a national outage record and evaluates the forecasts by the decisions they support rather than by prediction accuracy alone. We model outage occurrence and severity for counties across the contiguous United States from 2022 to 2024, using forecasts from the NOAA/CIRA archive of AI weather predictions (Radford et al., 2025) at lead times of 24 to 120 hours. We then assess what these forecasts are worth to a utility that must decide when to request mutual assistance crews.

The study makes four contributions. First, it analyses when crews should be committed. For each lead time, we measure the share of observed outage burden captured by staging crews in the counties ranked highest by the model. Paired resampling shows that the loss between three and five days is significant in all analyses, while the loss within the first three days is significant only when burden is limited to outages that have not yet started. We also report the crew availability ratio at which early commitment stops paying off, which requires no assumption about how availability declines when the request is delayed. This extends the forecast timing framework that Regnier and Harr (2006) and Regnier (2008) developed for hurricane evacuation to the commitment of infrastructure resources. The two problems differ, because a delayed evacuation faces a growing hazard, whereas a delayed crew request faces a shrinking pool of crews. We also express this analysis in economic terms without assuming a value of lost load, using potential economic value across a range of cost-loss ratios (Murphy, 1977; Richardson, 2000, 2001; Wilks, 2001) and the break-even staging cost per county-day. Second, it identifies and quantifies temporal leakage in antecedent land surface predictors. Evaluating these predictors at the forecast valid time instead of the issue time inflates their skill substantially. The inflation is concentrated in rolling window quantities, whose values at valid time and at issue time become almost uncorrelated at five days. Correcting the leakage reverses the conclusion that land surface state outperforms forecast meteorology at long lead times. The diagnostic is simple and can be applied to any impact forecasting study that uses antecedent conditions.

Third, it shows that gains in forecast skill do not necessarily produce gains in decisions. Adding land surface predictors improves occurrence skill considerably but does not significantly change captured outage burden at any lead time. Attribution analysis (Lundberg and Lee, 2017) links this gap to the static component of the land surface group, whose share of attribution increases as the forecast degrades. The difference between forecast skill and forecast value is well known in forecast verification (Murphy, 1977; Richardson, 2000), but it has rarely been examined in outage prediction. Fourth, it shows that prediction intervals can fail when the mix of hazards changes. Intervals built by conformalized quantile regression (Romano et al., 2019) have correct overall coverage but fail badly for individual hazard classes, because the calibration year had no major hurricane landfall on the US mainland and the test year had three. Calibration by hazard class (Vovk, 2013) restores coverage at a small cost in interval width, but only as a diagnostic, since hazard class is assigned after the event. Adding the training year to the calibration sample reduces coverage more than the shift it was meant to correct.

The remainder of this paper is organised as follows. Section 2 describes the data, the predictive model, the evaluation methods and the decision analysis. Section 3 presents and discusses the results and the limitations of the study, and Section 4 concludes.