The Project Scheduling Interdiction Problem with Delay Groups

Fei Wu, Erik Demeulemeester, Jannik Matuschke

Abstract

Large-scale projects are frequently delayed by correlated disruptions: when a shared input such as a common supplier, a specialized team, or a supporting platform degrades, all dependent activities are slowed down simultaneously. This paper introduces delay groups to capture such disruptions: a delay group is a set of activities whose delays stem from a common cause, described jointly by an uncertainty set. Our model takes the perspective of an interdictor that, subject to a budget of k groups, selects which groups to disrupt so as to maximize the project makespan. The interdictor can extend activity durations within each disrupted group by delays from a group-specific uncertainty set, while non-disrupted activities keep their nominal duration. We study the complexity of the resulting Project Scheduling Interdiction Problem with Delay Groups (PSIP-DG), which provides a worst-case stress test of the schedule. The problem is computationally intractable (NP-hard) for general polyhedral uncertainty sets, even for a single delay group with a continuous knapsack constraint. For budgeted uncertainty sets, we prove NP-hardness both when all activities of a disrupted group are delayed and when only one activity per group may be delayed, and derive an inapproximability bound of 1−1/e+ϵ1 - 1/e + \epsilon for the former case. We further develop a greedy heuristic with approximation guarantee k and two structure-based heuristics with initializations and neighborhoods from tractable special cases. Experiments on 5,000-activity networks show that the heuristics match the solution quality of an exact solver at substantially lower running times, in some cases finding strictly better solutions.

Keywords: Project scheduling; Interdiction; Delay groups; Computational complexity; Robust optimization

1. Introduction

Project scheduling is a part of project management that determines the sequence or scheduling plan for a series of related activities that are constituents of the project. In the absence of resource constraints, the critical path determines the makespan of the project (Goldratt, 1997). Delays of individual activities have therefore long been the natural unit of analysis when assessing a schedule's robustness. In large-scale projects, however, a disruption typically affects several activities at once. Activities often share a common enabler, a supplier delivering critical components, a team of specialists supervising several tasks, or a platform supporting parallel operations, and when that enabler degrades, all dependent activities are slowed down together. The 2020–2023 global semiconductor shortage illustrates this at an industry scale: as the supply of individual chip families tightened, manufacturers did not halt production but operated at a reduced pace, with component lead times prolonged by several months (Mohammad et al., 2022). The development of the Boeing 787 shows the same mechanism within a single project. Its assembly relied on approximately fifty tier-1 strategic suppliers, and shortages of shared components, most notably fasteners, simultaneously delayed the assembly activities depending on them; these correlated slowdowns accumulated along the precedence network, ultimately amounting to years of delay and billions in cost overruns (Tang et al., 2009).

Two features of these episodes matter for modeling. First, the affected activities were slowed down rather than stopped, so the disruption manifests as an increase in processing times. Second, the delays were correlated: activities sharing a dependency were hit together, though to different extents. Robust project scheduling models typically treat activity delays as independent perturbations. Under a common-cause disruption, however, several activities on the critical path, or on parallel paths, can be delayed at once, so an independence assumption can substantially understate the worst-case completion time. To capture this structure, we introduce delay groups: sets of activities whose delays are driven by a common underlying cause, with the joint delay within each group described by an uncertainty set.

We study this correlation structure in a precedence-constrained setting without resource constraints, so that any computational difficulty arises from the delay groups alone: our hardness results show that the problem is already NP-hard and hard to approximate in this basic setting, so these negative results extend to more complex settings, including resource-constrained variants. Moreover, the disruptions we model, namely the degradation of a shared enabler, slow down all dependent activities simultaneously rather than forcing them to queue for capacity, and are therefore naturally captured by processing time increases rather than by resource constraints.

Neither of these disruptions was caused by a deliberate attacker; the semiconductor shortage and Boeing's supplier failures arose from pandemic shocks and coordination failures. Their lesson, however, is best understood adversarially: the damage came from the combination of correlated delays, and the worst-case combination was never assessed in advance. Evaluating each shared dependency in isolation is insufficient, as the joint impact of simultaneous disruptions on the critical path can far exceed the sum of their individual effects. Identifying it is not a matter of simple enumeration: the difficulty stems both from selecting which groups to disrupt and from allocating delays within each group, and our complexity results show that the problem is NP-hard even in restricted settings, such as a single delay group or groups of at most two activities.

We therefore take an interdiction perspective: a hypothetical adversary, allowed to disrupt at most k delay groups with delays chosen from the uncertainty sets QrQ_{r}, selects the combination to maximize the project makespan. The resulting worst-case makespan serves as a stress test of the schedule: it quantifies how much the completion time can deteriorate under a bounded number of correlated disruptions. Szmerekovsky et al. (2023) argue that such worst-case risk assessment enables organizations to prepare not only for failures catastrophic to the project, but also for those catastrophic to the firm. The budget k and the uncertainty sets jointly keep the analysis from becoming overly conservative: bounding the number of simultaneously disrupted groups follows the budget-of-uncertainty principle that is standard in robust scheduling (Bertsimas and Sim, 2004; Bruni et al., 2017; Bold and Goerigk, 2021). Modeling delays via uncertainty sets rather than via probability distributions is also motivated by informational considerations. For one-off projects such as new aircraft development, the joint probability distribution of such delays is practically impossible to estimate. What project managers can assess, however, is which activities share a common dependency and the plausible range of the resulting delays, and these are exactly the inputs our model requires. The output of the model is directly actionable: it identifies the k most vulnerable delay groups and the associated worst-case completion time, indicating where robustness investments such as backup suppliers, redundant expertise, or schedule buffers yield the greatest protection. We call the resulting problem the Project Scheduling Interdiction Problem with Delay Groups (PSIP-DG).

Literature review. Robust optimization has been extensively studied for scheduling problems under polyhedral or budgeted uncertainty, building on the budget-of-uncertainty framework of Bertsimas and Sim (2004) introduced above. Subsequent work by Bertsimas et al. (2011) and Bertsimas and den Hertog (2022) extends this framework by formalizing a unified robust optimization approach and deriving tractable formulations for common uncertainty sets, including box, ellipsoidal, budgeted, and polyhedral sets. Building on this foundation, many studies have explored robust scheduling under budgeted uncertainty, with much of the research focusing on machine scheduling environments (Juvin et al., 2025); see Herroelen and Leus (2005) for a survey of project scheduling under uncertainty. In the context of project scheduling, Bruni et al. (2017) introduce a two-stage robust resource-constrained project scheduling problem with uncertain activity durations, solved via Benders decomposition. Bold and Goerigk (2021) later reformulate the inner adversarial problem as a longest-path problem and derive a compact MILP through duality, outperforming Benders-based methods in computational experiments; this formulation is subsequently extended to a multi-mode setting (Bold and Goerigk, 2022). While these robust resource-constrained models capture how scarce resources couple activities (Lambrechts et al., 2008), correlated delays arising from a common cause have not been modeled.

Beyond uncertainty, adversarial and interdiction-based perspectives have received growing attention. Brown et al. (2005) study the computational complexity of several project interdiction models and show that the special case of PSIP-DG with singleton groups (PSIP) can be solved via dynamic programming, whereas the problem becomes strongly NP-hard if the decision maker is allowed to expedite certain tasks. Brown et al. (2009) formulate the project interdiction problem as a Stackelberg game between a project manager and an attacker who aims to delay project completion; their bilevel optimization approach illustrates how limited interdiction resources can be allocated to maximally delay the project by targeting critical activities, which amounts to a longest-path interdiction problem on the project network. In these models, interdiction acts on individual activities, with the budget limiting the number or cost of activities that can be delayed; in PSIP-DG, by contrast, the interdictor attacks entire delay groups, whose delays are jointly constrained by an uncertainty set, so that a single interdiction decision affects several activities in a correlated manner.

In line with this work, Pinker et al. (2013) propose a secret project management model in which the project manager strategically invests resources in deception decisions to minimize the exposed time. They show that this problem is strongly NP-hard in the general sense and polynomially solvable when no deception is allowed. Pinker et al. (2014) further explore the computational complexity of this model, establishing hardness results and identifying tractable special cases. Gutin et al. (2015) investigate an interdiction game on a PERT network with stochastic (Markovian) task durations, formulating both static and dynamic strategies for the interdictor; under a memoryless assumption on activity durations, they derive tractable solution methods for each case. Unlike this stochastic model, which requires distributional assumptions on the task durations, our formulation, which is based on uncertainty sets, only requires support information on the delays. Klastorin and Mitchell (2013) develop a stochastic dynamic programming approach to optimize slack allocation and activity compression in anticipation of a single disruptive event. However, none of these works consider disruptions that are coupled across groups of tasks. To the best of our knowledge, this paper is the first to introduce delay groups into project scheduling interdiction models.

Our work is closely related to network interdiction problems. This class of problems is well understood for the case in which the delay scenarios are described by a bound on the total number of disruptions or on the cost of increasing individual durations (Brown et al., 2009; Israeli and Wood, 2002; Sefair and Smith, 2016; Wood, 2010); for reviews of the deterministic and stochastic network interdiction literature, we refer to Wood (2010), Smith and Song (2020), and Morton (2010). The problem we study is a longest-path interdiction problem, whereas most of the existing literature concerns shortest-path interdiction. Fulkerson and Harding (1977) consider a shortest-path interdiction model in which the length of each arc can be increased continuously and show that it can be solved by parametric linear programming, equivalent to a minimum-cost network flow problem, in polynomial time. When interdiction decisions are binary, however, the problem becomes NP-hard (Ball et al., 1989), and Boros et al. (2006) provide inapproximability bounds for several variants.

Another relevant problem is the NP-hard multiple-constraint shortest path (MCSP) problem, which aims to find the least-cost path between a pair of nodes such that the sum of additive edge weights does not exceed a specified limit (Garey and Johnson, 1979). Its single-constraint special case has been studied extensively, with numerous exact approaches, approximation schemes, and heuristics available in the literature (Lozano and Medaglia, 2013; Pugliese and Guerriero, 2013; Chen et al., 2008; Kuipers et al., 2002). In MCSP, however, the constraints restrict the chosen path directly; in PSIP-DG, by contrast, the group-selection variables interact with the path through the bilinear objective.

Our contribution and outline. In Section 2, we propose a new model for the project scheduling problem with delay groups and provide formal definitions for the uncertainty set within each group, including polyhedral and budgeted uncertainty sets. In Section 3, we identify some tractable cases of PSIP-DG, including the special case of PSIP-DG, in which each group has only one activity(PSIP). Prior work has shown that PSIP becomes NP-hard when interdiction costs are non-uniform and interdiction decisions are discrete, but remains polynomially solvable when interdiction levels are continuous under uniform costs. Our work fills a gap in the literature by analyzing a variant that simultaneously considers continuous interdiction decisions and non-uniform interdiction costs: we prove that this continuous PSIP with non-uniform interdiction costs is NP-hard, and this result directly implies the NP-hardness of PSIP-DG. Using two distinct reductions from the MAX k-COVER and 3-SAT problems, we show that PSIP-DG is NP-hard even for more restricted uncertain activity durations in the following two special cases: (i) all activities in the group VrV_r can be delayed, and (ii) exactly one activity is allowed to be delayed in each group. We further investigate the approximability of the general PSIP-DG problem and show that the problem does not admit a (1−1/e+ϵ)(1-1/e+\epsilon)-approximation for any ϵ>0\epsilon > 0 unless P=NPP = NP. The inapproximability result also holds for case (i).

For PSIP-DG with budgeted uncertainty sets, we develop approximation and heuristic algorithms in Section 4. We present a greedy heuristic with an approximation ratio exactly equal to the interdiction budget k, and we show that the joint impact of a set of delay groups is not determined by their individual contributions. We further propose two structure-based heuristics that search the two decision spaces of the problem: the subpath reoptimization search (SRS) iteratively improves a candidate longest path, initialized by relaxing the group restrictions, while the group selection search (GSS) iteratively improves the set of attacked groups, initialized by the exact per-group decomposition. In Section 5, we evaluate both heuristics against an exact MIP approach on networks ranging from 50 to over 5,000 nodes and up to 200,000 edges. The heuristics provide near-optimal solutions at a fraction of the running time; for large-scale instances, GSS matches the quality of the best solutions found by Gurobi within the one-hour time limit, in some cases finding strictly better ones. Finally, Section 6 concludes the paper and discusses future research directions.

References (38)