arXiv:2608.24779cs.LOAug 2026

Manuscript Offprint

arXiv:2608.24779

Cycle time minimization for the simple assembly line balancing problem under peak power constraints

Bao Gia Hoang, Tuyen Van Kieu, Khanh Van To

ABSTRACT

Peak power limits restrict concurrent tasks and may increase assembly-line cycle time. To the best of our knowledge, this study is the first to minimize cycle time for the simple assembly line balancing problem type 2 (SALBP-2) with a fixed number of workstations and a fixed limit on total instantaneous power. An exact satisfiability (SAT) method finds feasible schedules, searches systematically for shorter cycles, and proves optimality when possible. Two reproducible formulas define looser and tighter power limits for 72 cases based on the standard SALBP library, with Gurobi and CPLEX providing commercial MIP and CP comparisons. Relative to standard SALBP-2 optima, the two limits increase the best-known cycle time by 16.49% and 61.02% on average. The best-performing SAT configurations find a feasible solution for every case, solve more cases to optimality than each commercial solver, and when both prove optimality, are almost always faster under the reported settings.

KEYWORDS

assembly line balancing; cycle time minimization; peak power constraint; satisfiability; exact optimization

1. Introduction

The simple assembly line balancing problem (SALBP) assigns precedence-constrained tasks to ordered workstations. In SALBP-2, the number of workstations is fixed and the cycle time is minimized, thereby maximizing the production rate. Exact and heuristic procedures for SALBP-2 continue to be developed (Scholl and Becker 2006; Li, Kucukkoc, and Tang 2021; Álvarez-Miranda, Pereira, and Vilà 2024).

Energy-aware line balancing includes power or energy data for each task. The simple assembly line balancing problem with power-peak minimization (SALB3PM) fixes the number of workstations and the cycle time, then minimizes the highest total power drawn by the line at any time (Gianessi, Delorme, and Masmoudi 2019). Later mathematical-programming, heuristic, satisfiability (SAT), and maximum-

CONTACT Khanh Van To. Email: khanhtv@vnu.edu.vn satisfiability methods reduce this peak without changing the cycle time (Delorme, Gianessi, and Lamy 2023; Py et al. 2024; Zheng, Cherif, and Shibasaki 2024; Kieu et al. 2025).

A fixed peak power limit creates a different problem: given the number of workstations and the limit, the line designer seeks the shortest feasible cycle. Machine-scheduling studies also limit total power at each time while minimizing the overall completion time, or makespan (Fang et al. 2013; Wang and Wang 2019; Lv and Wang 2024; Yuan et al. 2026). However, they use job routes or machine assignments instead of assigning precedence-constrained tasks to ordered SALBP workstations.

This leaves an open problem in assembly-line balancing. To the best of our knowledge, no previous SALBP study has minimized cycle time when both the number of workstations and the limit on total instantaneous power are fixed. We call this problem the simple assembly line balancing problem with peak power constraints (SALBP-PPC).

Building on earlier SAT models (Py et al. 2024; Kieu et al. 2025), this study makes three contributions. First, it defines cycle time minimization under a fixed peak power limit and gives two reproducible formulas for setting the test limits. Second, it develops an exact SAT method that finds a feasible cycle, repeatedly searches for a shorter one, and proves optimality when possible. Third, it presents three ways to prevent tasks at the same workstation from overlapping and compares the resulting SAT methods with commercial mixed-integer programming (MIP) and constraint programming (CP) solvers on 72 benchmark cases.

References (33)