Manuscript Offprint
arXiv:2608.23509Energy and CO2 Footprint of Climate Model Intercomparison Projects
Abstract
Earth System Models (ESMs) rely heavily on High-Performance Computing (HPC) resources to simulate global climate. As these models evolve, their computational demands continue to grow, driven by three factors: (1) finer spatial grid resolutions, (2) the integration of complex biogeochemical processes (e.g., atmospheric chemistry, interactive vegetation, land use, and ice sheets), and (3) larger climate ensembles to manage uncertainty. Historically, growth in peak computing performance (FLOP/s) has outpaced improvements in energy efficiency (FLOP/Watt), increasing total HPC power consumption. Despite the central role of Model Intercomparison Projects (MIPs) in climate research, quantifying their computational and environmental costs has received limited systematic attention. This paper examines the evolution of climate model carbon accounting from voluntary post-hoc estimation in the Coupled Model Intercomparison Project phase 6 (CMIP6) to standardized accounting under the newly established CMIP7 Task Team on Energy Consumption. Using high-resolution Destination Earth simulations on MareNostrum 5, we empirically evaluate how different accounting boundaries (operational, active-only, and embodied carbon) impact reported energy, carbon emissions, and financial costs. Finally, we outline key methodological considerations for standardizing energy and carbon accounting for Model Intercomparison Projects (MIPs).
Keywords
Climate Modeling, CMIP7, HPC, Energy Efficiency, Carbon Footprint, Life Cycle Assessment
Barcelona Supercomputing Center (BSC)
Barcelona, Spain
Mario C. Acosta
Barcelona Supercomputing Center (BSC)
Barcelona, Spain
Universitat Politècnica de Catalunya (UPC)
Barcelona, Spain
the World Climate Research Programme (WCRP), rely on large-scale supercomputers to generate climate projections for the Intergovernmental Panel on Climate Change (IPCC). However, power availability and energy efficiency have emerged as critical infrastructure constraints. Between 2011 and 2025, top-tier supercomputers increased peak performance on average by approximately 64×, whereas energy efficiency (FLOP/Watt) improved by only 18×, driving average facility power draw up to 4× higher (Figure 1). This widening gap between throughput and energy efficiency—often termed the Power Wall [14]—makes energy consumption and carbon emissions critical metrics alongside scientific time-to-solution.
Average TOP500 Metrics (CPU-only Systems): Change Factor

Figure 1: Top500 HPC list (top500.org) averaged change factor from November 2011 to November 2025 (retrieved March 2025).
For Earth System Models (ESMs), power and energy limits directly constrain execution at scale. Advancing climate projections requires scaling compute resources across three primary dimensions, each compounding overall energy demand:
LOCO 2026: 2nd International Workshop on Low Carbon Computing, Lancaster, UK 2026.
LOCO 2026: 2nd International Workshop on Low Carbon Computing, September 10-11, 2026, Lancaster, UK Sergi Palomas, Pablo Aparici, Gladys Utrera, and Mario C. Acosta
• Spatial Resolution: Finer grid spacing resolves mesoscale atmospheric and oceanic structures with higher fidelity. However, smaller grid cells require shorter integration time steps, steeply increasing the total floating-point operations per Simulated Year (SY).
• Model Complexity: Modern ESMs integrate interactive biogeochemistry, atmospheric chemistry, dynamic vegetation, and ice-sheet dynamics. Coupling these physics sub-models introduces synchronization and communication overheads that can reduce parallel efficiency.
• Ensemble Scale: Characterizing scientific uncertainty requires executing multi-model, multi-member ensemble matrices across international modeling centers, multiplying total core-hours and energy consumption.
Despite the scale of these computational workloads, energy and carbon accounting in climate science has historically received little attention. However, computational carbon accounting has gained significant traction in machine learning and general High-Performance Computing (HPC). Early carbon estimation in deep learning by Strubell et al. [13] relied on coarse grid averages and static Power Usage Effectiveness (PUE) estimates. Later, Patterson et al. [11] showed that using peak chip efficiency overestimates real workload efficiency by to , emphasizing the need for full-rack power measurements. In HPC, Li et al. [9] and Masciari et al. [10] demonstrated that hardware counters (e.g., RAPL, NVML) effectively capture active application power, whereas job schedulers often lack detailed facility PUE integration. Furthermore, studies on dynamic grid carbon intensity [9, 11] revealed that annual average emission factors hide large daily fluctuations, inspiring carbon-aware job scheduling [10]. Beyond operational energy, Wu et al. [17] and Li et al. [9] showed that as electricity grids get cleaner, Scope 3 embodied carbon from hardware manufacturing accounts for a large share (30%–50%+) of total lifetime emissions. These insights directly inform the carbon accounting choices needed for climate modeling.
To address this gap, the climate modeling community is establishing standardized reporting frameworks. This paper analyzes the transition from voluntary energy reporting in CMIP6 to standardized accounting under the CMIP7 Task Team on Energy Consumption. Using high-resolution Destination Earth simulations on MareNostrum 5, we empirically demonstrate how operational, active-only, and embodied carbon accounting boundaries influence reported energy use, carbon footprint, and financial costs. Finally, we discuss key methodological challenges in standardizing these metrics for Model Intercomparison Projects (MIPs).
2 Context: Quantifying Model Intercomparison Project Computational Costs
2.1 CMIP6 Energy and Footprint
During the sixth phase of CMIP (CMIP6) [7], completed in 2021, 47 participating modeling centers produced petabytes of standardized climate output. A subset of modeling centers voluntarily coordinated under the IS-ENES3 project to collect computational performance metrics and operational costs across diverse HPC platforms [1].
To evaluate the environmental impact of CMIP6, Acosta et al. [1] gathered metrics differentiating between useful computational execution (simulations producing published scientific data) and total execution (encompassing spin-up phases, calibration sweeps, and discarded runs). Carbon Footprints (tCO ) were evaluated by combining useful Simulated Years (SY), facility Power Usage Effectiveness (PUE), and institution-specific energy supplier conversion factors (kWh → CO ).
Across the 8 institutions (out of 45) that reported complete data, the total operational carbon footprint reached 1,692 tCO .
Figure 2 illustrates total energy consumption, useful core-hours, and carbon footprint (tCO e) across reporting CMIP6 centers. The data reveal substantial disparities driven by facility efficiency and regional energy grids:
• Green Tariffs and Grid Carbon Intensity: Notably, NERC reported a zero operational carbon footprint due to procuring electricity under a 100% green tariff agreement. Similarly, CERFACS, UKMO, and IPSL benefited from low carbon emissions per kWh from their regional energy suppliers.
• Facility Power Usage Effectiveness (PUE): Facility efficiency varied significantly. DKRZ, MPI-M, and NERC reported highly efficient facilities with PUE < 1.2, whereas CERFACS, IPSL, EC-Earth, and UKMO reported significantly higher values. CMCC reported the highest PUE (1.84 for the Zeus supercomputer), making it the least power-efficient machine in the collection.

Figure 2: Total Energy vs. Core-Hours across seven tracking modeling centers participating in CMIP6. Bubble size is proportional to total carbon footprint equivalent (tCO e). Data adapted from Acosta et al. [1].
2.2 The CMIP7 Task Team Framework
To transition climate modeling from voluntary reporting to systematic carbon accounting, the World Climate Research Programme (WCRP) formally established the CMIP7 Task Team on Energy Consumption and Carbon Footprint [2, 16]. The task team defines reporting guidelines for all participating MIPs.
Rather than tracking only published production runs, CMIP7 requests data across production, tuning, and discarded simulations to capture the total computational effort of a modeling campaign [2].
Energy and CO₂ Footprint of Climate Model Intercomparison ProjectOCO 2026: 2nd International Workshop on Low Carbon Computing, September 10-11, 2026, Lancaster, UK
Carbon footprint accounting adopts the core formulation established during CMIP6 [1], scaling job energy consumption by facility Power Usage Effectiveness (PUE) and site-specific regional grid emission factors:
CMIP7 refines this methodology by prioritizing dynamic (active-only) energy consumption—measured via hardware counters (e.g., Intel RAPL, NVIDIA NVML, AMD ROCm-SMI) or scheduler logs—to separate workload power draw from baseline system idle power. The current CMIP7 reporting scope focuses on operational simulation runs on regional power grids, excluding Scope 3 embodied hardware emissions.
3 Workload Analysis: Climate Digital Twin Simulation Costs
Simulating the Destination Earth model configuration at 5 km resolution on MareNostrum 5 requires 475 compute nodes to achieve a throughput of 1 Simulated Year Per Day (SYPD) [4]. To evaluate the computational, environmental, and financial costs of this workload, three accounting boundaries can be applied:
(1) Operational Accounting: Captures full node power draw and facility overhead (PUE) during execution to reflect actual grid electricity demand and Scope 2 emissions.
(2) Active-Only Accounting: Subtracts baseline idle power to isolate dynamic energy consumption, evaluating software and kernel efficiency.
(3) Embodied and Life Cycle Accounting: Extends the boundary to include upstream Scope 3 hardware manufacturing emissions and Total Cost of Ownership (TCO) across the system’s lifespan.
The following subsections detail the hardware parameters, data sources, and calculations for each boundary.
3.1 Operational Accounting
Operational accounting measures total hardware resource utilization and facility power draw during simulation execution:
Given an empirical average power draw of 900 W per node (measured across over 2,000 baseline runs using the Energy Aware Runtime (EAR) monitoring framework [3]), total operational energy consumption is:
11,400 node-hours/SY × 0.900 kWh/node – hour = 10.3 MWh/SY
Using Spain’s 2025 grid carbon intensity (135 g CO₂/kWh, retrieved from Electricity Maps [5]) and MareNostrum 5’s facility Power Usage Effectiveness (PUE = 1.08 [6]), the operational Scope 2 carbon footprint is:
This metric captures the total operational electricity and Scope 2 emissions required to execute the simulation, reflecting real facility utility demand.
3.2 Active-Only (Dynamic) Accounting
Active-only accounting isolates dynamic energy and emissions by excluding baseline infrastructure overheads. On MareNostrum 5, an idle compute node draws 390 W (measured via EAR on an allocated node in an idle state over time). Subtracting this baseline yields an active node power draw of 510 W (900 W – 390 W):
11,400 node-hours/SY × 0.510 kWh/node – hour = 5.81 MWh/SY
Applying the same PUE and grid intensity, the isolated dynamic Scope 2 carbon footprint is:
Crucially, active-only accounting reduces both energy and emissions by 43.5% compared to operational accounting. While this metric isolates software and kernel efficiency for developers, it excludes the idle power needed to keep the cluster available.
3.3 Embodied Carbon and Total Cost of Ownership Accounting
Embodied accounting expands the boundary to include upstream Scope 3 emissions and capital costs (CapEx) from hardware manufacturing and procurement. As reported in [12], the total embodied carbon of MareNostrum 5's General Purpose Partition (GPP) is 22,614 tCO₂e. Assuming standard design expectations for the system—a 5-year lifecycle at 80% target utilization—total lifetime capacity across its 7,600 nodes is:
Dividing embodied carbon by total lifetime node-hours yields the manufacturing carbon intensity:
Multiplying this rate by the 11,400 node-hours required for one simulated year adds an embodied carbon footprint of:
Combining embodied manufacturing (967.4 kg) and operational Scope 2 emissions (1,501.7 kg) yields a total life-cycle carbon footprint of 2,469.1 kg CO₂e/SY.
Alongside embodied carbon, financial accounting captures hardware purchase costs plus operational maintenance. Based on the public Total Cost of Ownership (TCO) of €202M for MareNostrum 5's GPP [6] over its 5-year lifecycle at 80% utilization, the TCO per node-hour is:
LOCO 2026: 2nd International Workshop on Low Carbon Computing, September 10-11, 2026, Lancaster, UK Sergi Palomas, Pablo Aparici, Gladys Utrera, and Mario C. Acosta
This results in a Total Cost of Ownership per simulated year of:
0.76 €/node-hour × 11,400 node-hours/SY = 8,664 €/SY
This metric includes the upfront capital investment (CapEx) required to build the supercomputer alongside ongoing operational costs, showing that hardware purchase is a primary cost driver.
4 Challenges and Discussion
4.1 Comparative Analysis of Accounting Boundaries
The empirical results in Section 3 illustrate how the choice of accounting boundary alters reported metrics across energy, carbon, and financial dimensions:
• Active-Only Boundary (Dynamic Workload): Isolates dynamic power (510 W), energy (5.81 MWh/SY), and Scope 2 carbon (847.7 kg CO₂e/SY) for algorithm and kernel optimization. While valuable for software developers, it underestimates facility energy consumption and real emissions by 43.5% by omitting baseline idle power (390 W/node).
• Operational Boundary (Facility Allocation): Captures full node electricity consumption (10.3 MWh/SY) and total operational Scope 2 carbon (1,501.7 kg CO₂e/SY). It reflects true datacenter utility demand and grid emissions, but remains sensitive to regional grid carbon intensity and omits hardware manufacturing debt.
• Embodied and Life Cycle Boundary (Full System Debt): Integrates Scope 3 manufacturing debt (967.4 kg CO₂e/SY), resulting in a 1.64× multiplier over operational carbon (totaling 2,469.1 kg CO₂e/SY), and accounts for the Total Cost of Ownership (€8,664/SY, based on €202M in system procurement). This comprehensive boundary prevents carbon leakage and provides full accountability for institutional planning.
4.2 Methodological Challenges
4.2.1 Measurement Accuracy vs. Usability. Accurately profiling energy across heterogeneous HPC clusters while maintaining cross-platform comparability remains challenging. Low-level profiling tools (EAR [3], MERIC [15], LIKWID [8]) offer detailed measurement capabilities but add workflow complexity. Consequently, modeling teams often rely on job-scheduler logs, which vary in sampling frequency and boundary scope across centers.
4.2.2 Standardization and Dynamic Grid Signals. Establishing a unified framework requires consistent definitions for subsystem boundaries, sampling intervals, and idle power allocation. In addition, current practices rely on static annual grid averages (135 g CO₂/kWh), which ignore short-term fluctuations in renewable energy. However, adding carbon-aware scheduling to HPC introduces a key challenge: because supercomputing centers operate under high capital investments and must maintain near 100% utilization, delaying a job often leads to zero-sum displacement, where another queued job simply fills the slot during high-emission periods. Genuine net emission reductions therefore require shifting workloads geographically across international centers or applying dynamic power capping.
4.3 Recommendations for CMIP7 and Beyond
Based on our empirical findings and literature analysis, we propose three recommendations for standardizing energy reporting in CMIP7:
(1) Mandate Multi-Boundary Reporting: CMIP7 should establish Operational Carbon as the core baseline reporting metric while recommending Embodied Carbon to be reported as an additive Scope 3 component.
(2) Automate Scheduler-Level Measurement: HPC facility operators should integrate automated energy measurement into batch schedulers (e.g., Slurm) to capture metered node power and idle baselines without requiring manual code instrumentation.
(3) Incentivize Geographic and Carbon-Aware Scheduling: Supercomputing centers and climate consortia should leverage dynamic grid carbon intensity signals to coordinate spatial shifting of flexible ensemble workloads across distributed international facilities and explore carbon-aware power capping.
5 Conclusions
As climate modeling enters the kilometer-scale regime, evaluating performance solely by throughput metrics such as Simulated Years Per Day (SYPD) or total core-hours is no longer sufficient. Environmental footprint accounting must be integrated into standard benchmarking practices. Building upon the voluntary reporting in CMIP6, the CMIP7 Task Team on Energy Consumption provides a framework for standardized pre-execution energy profiling across global HPC facilities.
Our evaluation of Destination Earth on MareNostrum 5 demonstrates that reported footprints depend heavily on boundary selection. Active-only accounting (5.81 MWh/SY, 847.7 kg CO₂e/SY) isolates dynamic kernel efficiency, whereas operational accounting (10.3 MWh/SY, 1,501.7 kg CO₂e/SY) reflects total facility utility demand. Furthermore, full life-cycle accounting—adding manufacturing emissions (967.4 kg CO₂e/SY) and TCO (€8,664/SY)—increases the total footprint by 1.64× to 2,469.1 kg CO₂e/SY, showing that Scope 3 embodied debt and capital costs are major factors.
Addressing current energy measurement challenges requires balancing low-level hardware profiling precision against job-scheduler usability, as well as transitioning from static annual grid averages to dynamic real-time carbon tracking.
To advance energy accountability, we advocate a three-part strategy for CMIP7: (1) mandating operational carbon as the baseline metric with embodied carbon as an additive Scope 3 multiplier, (2) automating energy measurement within batch schedulers, and (3) adopting carbon-aware scheduling for ensemble simulations. Standardizing these methodologies will help embed energy and carbon efficiency into future HPC system design and climate modeling practices.
Acknowledgments
This work has received funding from the European High Performance Computing Joint Undertaking (EuroHPC JU) and the European Union through the ESiWACE3 project under grant agreement No. 101093054. This work was also supported by the Destination
Energy and Footprint of Climate Model Intercomparison Project OCO 2026: 2nd International Workshop on Low Carbon Computing, September 10-11, 2026, Lancaster, UK
Earth (DestinE) initiative of the European Commission. The authors also gratefully acknowledge the computational resources and support provided by the Barcelona Supercomputing Center (BSC) on the MareNostrum 5 supercomputer.
References
[1] M. C. Acosta, S. Palomas, S. V. Paronuzzi Ticco, G. Utrera, J. Biercamp, P.-A. Bretonniere, R. Budich, M. Castrillo, A. Caubel, F. Doblas-Reyes, I. Epicoco, U. Fladrich, S. Joussaume, A. Kumar Gupta, B. Lawrence, P. Le Sager, G. Lister, M.-P. Moine, J.-C. Rioual, S. Valcke, N. Zadeh, and V. Balaji. 2024. The computational and energy cost of simulation and storage for climate science: lessons from CMIP6. Geoscientific Model Development 17, 8 (2024), 3081–3098. doi:10.5194/gmd-17-3081-2024
[2] Mario C. Acosta, Sergi Palomas, Sophie Valcke, Pierre-Antoine Bretonnière, Muhammad Amjad, Asad Mahmood, Paul Smith, David Hassell, and Frédéric Bonou. 2025. Metrics to quantify performance, energy and footprint of CMIP7 simulations. doi:10.5281/zenodo.17522934
[3] Julita Corbalan, Luigi Brochard, Jalal Lakhlili, Marco d'Amico, Oriol Vidal, and Jordi Aneas. 2025. Energy Data Center Monitoring and Management with EAR. In Proceedings of the 16th ACM International Conference on Future and Sustainable Energy Systems (E-Energy '25). Association for Computing Machinery, New York, NY, USA, 915–920. doi:10.1145/3679240.3735105
[4] F. J. Doblas-Reyes, J. Kontkanen, I. Sandu, M. Acosta, M. H. Al Turjmam, I. Alsina-Ferrer, M. Andrés-Martínez, C. Anerdi, L. Arriola, M. Axness, M. Batlle Martín, P. Bauer, T. Becker, D. Beltrán, S. Beyer, H. Bockelmann, P.-A. Bretonnière, S. Cabaniols, S. Caprioli, M. Castrillo, A. Chandrasekar, S. Cheedela, V. Correal, E. Danovaro, P. Davini, J. Enkovaara, C. Frauen, B. Früh, A. Gaya Ávila, P. Ghinassi, R. Ghosh, S. Ghosh, I. González, K. Grayson, M. Griffith, I. Hadade, C. Haine, C. Hartick, U.-U. Haus, S. Hearne, H. Järvinen, B. Jiménez, A. John, M. Juchem, T. Jung, J. Kegel, M. Kelbling, K. Keller, B. Kinoshita, T. Kiszler, D. Klocke, L. Kluft, N. Koldunov, T. Kölling, J. Kolstela, L. Kornblueh, S. Kosukhin, A. Lacima-Nadolnik, J. J. Leal Rojas, J. Lehtiranta, T. Lunttila, A. Luoma, P. Manninen, A. Medvedev, S. Milinski, A. Mohammed, S. Müller, D. Naryanappa, N. Nazarova, S. Niemelä, B. Niraula, H. Nortamo, A. Nummelin, M. Nurisso, P. Ortega, S. Paronuzzi, X. Pedruzo-Bagazgoitia, C. Pelletier, C. Peña, S. Polade, H. K. Pradhan, R. Quintanilla, T. Quintino, T. Rackow, J. Räisänen, M. M. Rajput, R. Redler, B. Reuter, N. Rocha Monteiro, F. Roura-Adserias, S. Ruppert, S. Sayed, R. Schnur, T. Sharma, D. Sidorenko, O. Sievi-Korte, A. Soret, C. Steger, B. Stevens, J. Streffing, J. Sunny, L. Tenorio, S. Thober, U. Tigerstedt, O. Tinto, J. Tonttila, H. Tuomenvirta, L. Tuppi, G. Van Thielen, E. Vitali, J. von Hardenberg, I. Wagner, N. Wedi, J. Wehner, S. Willner, X. Yepes-Arbós, F. Ziemen, and J. Zimmermann. 2026. The Destination Earth digital twin for climate change adaptation. Geoscientific Model Development 19, 7 (2026), 2821–2848. doi:10.5194/gmd-19-2821-2026
[5] Electricity Maps. 2025. Spain Electricity Grid Carbon Intensity Data and Methodology. Accessed: 2026. https://app.electricitymaps.com/map/zone/ES/all/yearly
[6] European High Performance Computing Joint Undertaking (EuroHPC JU). 2023. MareNostrum 5 Supercomputer Inauguration and System Specifications. Accessed: 2026.
https://eurohpc-ju.europa.eu/supercomputers/marenostrum_5_en
[7] V. Eyring, S. Bony, G. A. Meehl, C. A. Senior, B. Stevens, R. J. Stouffer, and K. E. Taylor. 2016. Overview of the Coupled Model Intercomparison Project Phase 6 (CMIP6) experimental design and organization. Geoscientific Model Development 9, 5 (2016), 1937–1958. https://gmd.copernicus.org/articles/9/1937/2016/
[8] Karlo Kraljic, Daniel Kerger, and Martin Schulz. 2022. Energy efficient frequency scaling on GPUs in heterogeneous HPC systems. In International Conference on Architecture of Computing Systems. Springer, 3–16.
[9] Baolin Li, Rohan Basu Roy, Daniel Wang, Siddharth Samsi, Vijay Gadepally, and Devesh Tiwari. 2023. Toward Sustainable HPC: Carbon Footprint Estimation and Environmental Implications of HPC Systems. In Proceedings of the International Conference for High Performance Computing, Networking, Storage and Analysis (Denver, CO, USA) (SC '23). Association for Computing Machinery, New York, NY, USA, Article 19, 15 pages. doi:10.1145/3581784.3607035
[10] Elio Masciari and Enea Vincenzo Napolitano. 2024. The Environmental Cost of High Performance Computing System Simulation. In 2024 32nd Euromicro International Conference on Parallel, Distributed and Network-Based Processing (PDP). 289–292. doi:10.1109/PDP62718.2024.00048
[11] David A. Patterson, Joseph Gonzalez, Quoc V. Le, Chen Liang, Lluis-Miquel Munguia, Daniel Rothchild, David R. So, Maud Texier, and Jeff Dean. 2021. Carbon Emissions and Large Neural Network Training. CoRR abs/2104.10350 (2021). arXiv:2104.10350 https://arxiv.org/abs/2104.10350
[12] Varsha Rao and Andrew A. Chien. 2025. Modeling the Carbon Footprint of HPC: The Top 500 and EasyC. In Proceedings of the SC '25 Workshops of the International Conference for High Performance Computing, Networking, Storage
and Analysis (SC Workshops '25). Association for Computing Machinery, New York, NY, USA, 2032–2040. doi:10.1145/3731599.3767567
[13] Emma Strubell, Ananya Ganesh, and Andrew McCallum. 2019. Energy and Policy Considerations for Deep Learning in NLP. In Proceedings of the 57th Annual Meeting of the Association for Computational Linguistics, Anna Korhonen, David Traum, and Lluis Márquez (Eds.). Association for Computational Linguistics, Florence, Italy, 3645–3650. doi:10.18653/v1/P19-1355
[14] Oreste Villa, Daniel R. Johnson, Mike Oconnor, Evgeny Bolotin, David Nellans, Justin Luitjens, Nikolai Sakharnykh, Peng Wang, Paulius Micikevicius, Anthony Scudiero, Stephen W. Keckler, and William J. Dally. 2014. Scaling the Power Wall: A Path to Exascale. In SC '14: Proceedings of the International Conference for High Performance Computing, Networking, Storage and Analysis. 830–841. doi:10.1109/SC.2014.73
[15] Ondrej Vysocky, Martin Beseda, Lubomír Ríha, Jan Zapletal, Michael Lysaght, and Venkatesh Kannan. 2018. MERIC and RADAR Generator: Tools for Energy Evaluation and Runtime Tuning of HPC Applications. In High Performance Computing in Science and Engineering, Tomáš Kozubek, Martin Čermák, Petr Tichý, Radim Blaheta, Jakub Šítek, Dalibor Lukáš, and Jiří Jaroš (Eds.). Springer International Publishing, Cham, 144–159.
[16] World Climate Research Programme (WCRP). 2026. CMIP7 Task Team: Energy Consumption. Accessed: 2026-06-30. https://wcrp-cmip.org/cmip7-task-teams/energy-consumption/
[17] Carole-Jean Wu, Ramya Raghavendra, Udit Gupta, Bilge Acun, Newsha Ardalani, Kiwan Maeng, Gloria Chang, Fiona Aga Behram, James Huang, Charles Bai, Michael Gschwind, Anurag Gupta, Myle Ott, Anastasia Melnikov, Salvatore Candido, David Brooks, Geeta Chauhan, Benjamin C. Lee, Hsien-Hsin S. Lee, Bugra Akyildiz, Maximilian Balandat, Joe Spisak, Ravi Jain, Mike Rabbat, and Kim M. Hazelwood. 2021. Sustainable AI: Environmental Implications, Challenges and Opportunities. CoRR abs/2111.00364 (2021). arXiv:2111.00364 https://arxiv.org/abs/2111.00364