ABSTRACT

The increasing penetration of renewable energy and rising electricity demand are driving the need to integrate new buses and transmission lines into transmission grids. These trends are reshaping transmission expansion planning (TEP), motivating the development of effective methodologies to manage the resulting complexity. This paper introduces the longest shortest-path connection (LSPC) algorithm, a graph-based method to enhance the mixed-integer linear programming disjunctive formulation of TEP using valid inequalities (VIs). Traditional approaches for determining big-M coefficients in disconnected TEP networks typically rely on solving the computationally intensive longest path problem (LPP). In contrast, LSPC circumvents these limitations by efficiently identifying relevant power-flow paths between disconnected buses within the expansion network. We demonstrate that the VIs generated from these identified paths dominate those derived from LPP-based methods and other existing approaches.

Keywords Transmission expansion planning · Mixed-integer linear programming · Valid inequalities · New-bus integration

1 Introduction

Transmission expansion planning (TEP) entails adding transmission lines within and between systems to accommodate future demand growth at the lowest possible cost [1]. The strategic importance of TEP in power systems cannot be overstated, given its long-term implications for system operations. The evolving energy landscape, marked by renewable integration, large-scale generation projects, and increasing demand from industrial facilities and data centers, has significantly increased the complexity of TEP and the need for more effective solution methods [2, 3].

TEP is often formulated using a linear approximation model, namely Direct-Current Optimal Power Flow (DC-OPF), which is widely applied in power system optimization (e.g., [4],[5],[6]). This linearization is obtained by assuming uniform voltage magnitudes, minimal angle differences, and disregarding reactive power, considering the low conductance of transmission lines [7]. These simplifications provide an effective trade-off between simplicity and accuracy, making them suitable for TEP, where operational considerations are less critical due to the long-term planning horizon and extensive power transmission distances [8].

The introduction of discrete decisions to DC-OPF transforms it from a linear program (LP) into a mixed-integer linear program (MILP), which is generally intractable (i.e., NP-hard [9]). Its complexity explains the emphasis on metaheuristics and other inexact methods (e.g., [10],[11],[12],[13]), even though these approaches do not provide formal guarantees of the solution quality. Hybrid methods for DC-TEP that couple heuristics with branch-and-bound algorithms (e.g., [14],[15],[16]) have been explored. However, despite having theoretical guarantees, their high computational cost limits them to smaller problems, hindering their practical scalability. Benders' decomposition is another popular method for solving DC-TEP that guarantees optimal solutions ([17],[18],[19],[20]), but it suffers from slow convergence in large-scale problems.

A complementary exact approach is to strengthen the MILP formulation. DC-TEP is commonly formulated using big-M constraints that couple line-investment decisions with physical constraints across the incident buses. The choice of the big-M bounds can substantially affect formulation strength, as overly large values weaken the LP relaxation and increase the computational burden of exact methods. Cutting plane methods can tighten these bounds. Their computational benefits have been widely demonstrated in power systems optimization problems with discrete decisions, such as optimal transmission switching and unit commitment (e.g., [21, 22, 23, 24]). In contrast, they have received little attention in DC-TEP. The few works that attempt to strengthen big-M bounds are either limited to already-connected networks or otherwise lead to computationally intractable procedures (e.g., [25]).

Deriving tight big-M bounds for candidate-line endpoints—and, more generally, for any bus pair—relies on identifying relevant power-flow paths that connect them. In an already-connected network, any path comprised of existing lines between the pair provides a valid bound. In contrast, identifying relevant paths becomes more challenging when connectivity between buses depends on which investment options are chosen. Existing approaches generally assume that obtaining a provably tight bound in these situations requires solving the longest path problem (LPP), which is NP-hard [26]. To address this challenge, this paper exploits structural properties of DC-TEP in restricted yet practically relevant expansion settings to identify the relevant paths and thereby derive the tightest big-M bounds efficiently.

The rest of the paper is organized as follows. Section 2 presents the DC-TEP formulation and introduces background concepts. Section 3 motivates the featured methodology, denoted as the longest shortest-path connection algorithm, to tackle situations that require new-bus integration. Section 4 provides a detailed description of this algorithm, along with proofs of correctness and complexity. Finally, Section 5 concludes with a summary of the contributions and directions for future work.